For journalists
and researchers
Everything here is free to use, including commercially, with attribution. There is no embargo, no login for the data, and no need to ask. If you are checking a number before you publish, or you think one is wrong, please get in touch — a correction is more use to us than a quiet retraction is to you.
Contact
press@energymap.app — corrections, data questions, or a number you want explained before you run it. If you are on deadline, say so in the subject line.
How to cite it
“energymap.app” is enough, and a link is appreciated. For a specific figure, cite the constituency page it came from and the date, because the underlying data is rebuilt weekly and revised by its publishers — for example: energymap.app, July 2026 data.
We are not the source of the underlying data and do not claim to be. Elexon, DESNZ, NESO and ONS publish it; what is ours is the constituency view, the reason join, the cleaning and the reconciliation. The method page says exactly which is which, so cite the primary source where you can.
How to check anything here
- Every project carries its planning application reference. That reference on the council's own register is the primary record — the decision notice, the officer's report and any refusal reasons. Neighbouring schemes often share a name, so the reference is the only reliable way to be sure you have the right one.
- Every seat's numbers are downloadable as JSON and CSV, including the mapping file that connects meters to sites, with a confidence grade on every row.
- The reconciliation shows our monthly volumes against NESO's own published figures. The build fails if any complete month diverges by more than 2%.
- Where the government's planning database and a council's register disagree, we drop the record rather than publish it, and say which and why in the exclusions file.
One caution worth printing. The planning database records that a decision was made and when, but never why. No page on this site states a reason for a refusal, and you should not infer one from it. That is in the council's decision notice.
Where the strongest constituency stories are right now
Data to July 2026. Each links to a briefing that names the projects, the developers, the decision-makers and the planning references.
Paid the most to switch off wind
| Constituency | Paid to switch off | MP |
|---|---|---|
| Inverness, Skye and West Ross-shire | £41m | Mr Angus MacDonald |
| Caithness, Sutherland and Easter Ross | £36m | Jamie Stone |
| Ayr, Carrick and Cumnock | £18m | Elaine Stewart |
| Moray West, Nairn and Strathspey | £17m | Graham Leadbitter |
| Orkney and Shetland | £15m | Mr Alistair Carmichael |
| Dumfriesshire, Clydesdale and Tweeddale | £15m | David Mundell |
| Dumfries and Galloway | £11m | John Cooper |
| Berwickshire, Roxburgh and Selkirk | £7.0m | John Lamont |
| East Renfrewshire | £4.6m | Blair McDougall |
| Angus and Perthshire Glens | £3.4m | Dave Doogan |
Largest battery refused planning
| Constituency | Refused | MP |
|---|---|---|
| Honiton and Sidmouth | 400 MW | Richard Foord |
| Dunstable and Leighton Buzzard | 350 MW | Alex Mayer |
| Carlisle | 340 MW | Ms Julie Minns |
| Ashford | 300 MW | Sojan Joseph |
| Dartford | 300 MW | Jim Dickson |
| Warrington South | 250 MW | Sarah Hall |
| Burnley | 245 MW | Oliver Ryan |
| North East Hampshire | 215 MW | Alex Brewer |
| Dumfriesshire, Clydesdale and Tweeddale | 207 MW | David Mundell |
| Lichfield | 200 MW | Dave Robertson |
Where the queue most dwarfs what was ever built
| Constituency | Waiting vs running | Waiting | MP |
|---|---|---|---|
| Tamworth | 57x | 113 MW | Sarah Edwards |
| Lichfield | 56x | 101 MW | Dave Robertson |
| Stone, Great Wyrley and Penkridge | 22x | 125 MW | Sir Gavin Williamson |
| Mid Buckinghamshire | 18x | 136 MW | Greg Smith |
| Rutland and Stamford | 16x | 379 MW | Alicia Kearns |
| North East Hampshire | 15x | 168 MW | Alex Brewer |
| Gainsborough | 12x | 583 MW | Sir Edward Leigh |
| North West Essex | 9x | 623 MW | Mrs Kemi Badenoch |
| Stoke-on-Trent South | 8x | 115 MW | Dr Allison Gardner |
| Central Suffolk and North Ipswich | 8x | 177 MW | Patrick Spencer |
Images
Every constituency has a 1200×630 share card, free to reproduce: energymap.app/cards/<ONS code>.png — for example S14000069.png. The map is screenshot-friendly at any size. If you need a chart or a cut of the data that does not exist yet, ask; it is usually quicker for us to generate than for you to rebuild.
Briefings
Each constituency has a two-page briefing in a newsroom edition — what is stuck, who holds the next decision, the planning references, story angles and how to check them. A free account opens the packaged briefings and their PDFs. Everything else on this site, including every figure and all the data, needs no account.