Dumfries and Galloway
Dumfries and Galloway was paid £11m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 132 days. A further 560 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 488,000 homes. A 40 MW battery approved at Kellwood Road in 2025 would store power that is currently wasted; it has not been built.
Ranks 7 of 650 for clean power approved and not built; 7 of 19 among seats with visible switch-off payments.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Blair Hill Wind FarmRES Limited | Onshore wind | 145 MW127,000 homes | Waiting 17 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2036 · planning ref ECU00004878 |
| Mid Moile Wind FarmEnergieKontor UK Limited | Onshore wind | 99 MW87,000 homes | Cannot connect to the grid until 2031, 6 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2031 · planning ref ECU00003405 |
| Quantans Hill Wind FarmVattenfall Wind Power Limited | Onshore wind | 96 MW84,000 homes | Waiting 3.5 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00003399 |
| Windy Standard III Wind Farm (Brockloch Rig Phase 2)Fred Olsen Renewables | Onshore wind | 88 MW77,000 homes | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00000335 |
| Glenvernoch Wind FarmEnergiekontor (UK) Limited | Onshore wind | 86 MW75,000 homes | Waiting 21 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2037 · planning ref ECU00004892 |
| Stranoch 2EDF Energy | Onshore wind | 84 MW73,000 homes | Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2026 · planning ref ECU00000710 |
| Shepherd's Rig Wind FarmBoralex/Infinergy | Onshore wind | 81 MW71,000 homes | Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00000735 |
| Troston LochEDF Energy Renewables | Onshore wind | 67 MW59,000 homes | Approved 6 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00001785 |
| Lorg WindfarmRWE Npower Renewables | Onshore wind | 64 MW56,000 homes | Cannot connect to the grid until 2027, 1 year after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2027 · planning ref ECU00003283 |
| Lairdmannoch Energy ParkWind2 / Octopus Energy | Onshore wind | 60 MW52,000 homes | Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004900 |
| Kilgallioch Windfarm (Extension)ScottishPower Renewables | Onshore wind | 50 MW44,000 homes | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00001996 |
| High Mark Wind Farm - Wind TurbinesWind Estate (UK) Ltd | Onshore wind | 50 MW44,000 homes | Applied in 2026, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005159 |
Plus 31 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Dumfries and Galloway | 560 MW | 695 MW | £11m |
| Dumfriesshire, Clydesdale and Tweeddale | 913 MW | 1,451 MW | £15m |
| Ayr, Carrick and Cumnock | 654 MW | 874 MW | £18m |
Dumfriesshire, Clydesdale and Tweeddale next door has 913 MW waiting, more than Dumfries and Galloway's 560 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call