CONSTITUENCY BRIEFING · ENERGYMAP.APP

Dumfries and Galloway

MP: John Cooper (Conservative) Scotland Data to July 2026

Dumfries and Galloway was paid £11m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 132 days. A further 560 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 488,000 homes. A 40 MW battery approved at Kellwood Road in 2025 would store power that is currently wasted; it has not been built.

Ranks 7 of 650 for clean power approved and not built; 7 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Blair Hill Wind FarmRES Limited Onshore wind 145 MW127,000 homes Waiting 17 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2036 · planning ref ECU00004878
Mid Moile Wind FarmEnergieKontor UK Limited Onshore wind 99 MW87,000 homes Cannot connect to the grid until 2031, 6 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2031 · planning ref ECU00003405
Quantans Hill Wind FarmVattenfall Wind Power Limited Onshore wind 96 MW84,000 homes Waiting 3.5 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00003399
Windy Standard III Wind Farm (Brockloch Rig Phase 2)Fred Olsen Renewables Onshore wind 88 MW77,000 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00000335
Glenvernoch Wind FarmEnergiekontor (UK) Limited Onshore wind 86 MW75,000 homes Waiting 21 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2037 · planning ref ECU00004892
Stranoch 2EDF Energy Onshore wind 84 MW73,000 homes Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2026 · planning ref ECU00000710
Shepherd's Rig Wind FarmBoralex/Infinergy Onshore wind 81 MW71,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00000735
Troston LochEDF Energy Renewables Onshore wind 67 MW59,000 homes Approved 6 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00001785
Lorg WindfarmRWE Npower Renewables Onshore wind 64 MW56,000 homes Cannot connect to the grid until 2027, 1 year after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2027 · planning ref ECU00003283
Lairdmannoch Energy ParkWind2 / Octopus Energy Onshore wind 60 MW52,000 homes Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004900
Kilgallioch Windfarm (Extension)ScottishPower Renewables Onshore wind 50 MW44,000 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00001996
High Mark Wind Farm - Wind TurbinesWind Estate (UK) Ltd Onshore wind 50 MW44,000 homes Applied in 2026, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005159

Plus 31 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Dumfries and Galloway 560 MW695 MW£11m
Dumfriesshire, Clydesdale and Tweeddale 913 MW1,451 MW£15m
Ayr, Carrick and Cumnock 654 MW874 MW£18m

Dumfriesshire, Clydesdale and Tweeddale next door has 913 MW waiting, more than Dumfries and Galloway's 560 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.