CONSTITUENCY BRIEFING · ENERGYMAP.APP

Gainsborough

MP: Sir Edward Leigh (Conservative) England Data to July 2026

Gainsborough has 583 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 212,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,345 homes.

Ranks 6 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Cottam Solar ProjectIsland Green Power Solar 600 MW218,000 homes Cannot connect to the grid until 2029, 5 years after it was approvedWho can move it: the grid operator (NESO) and National Grid · earliest connection 2029 · planning ref EN010133
Gate Burton - Solar & Energy Storage ParkLow Carbon Solar 531 MW193,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref EN010131
Tillbridge Solar Farm, Hemswell - Solar PanelsTillbridge Solar Limited Solar 500 MW182,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref EN010142
West Burton Solar ProjectIsland Green Power Solar 480 MW174,000 homes Cannot connect to the grid until 2028, 3 years after it was approvedWho can move it: the grid operator (NESO) and National Grid · earliest connection 2028 · planning ref EN010132
Barfield Lane, Reepham - Battery Energy Storage SystemFiskerton Bess Limited Battery 53 MW Waiting 2.9 years for a planning decisionWho can move it: West Lindsey Council · planning ref 147131
The Old Airfield Solar Photovoltaic FarmGrey Street Solar Limited Solar 50 MW18,000 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 142117
Airfield Farm - Solar ArrayEngena Limited Solar 50 MW18,000 homes Applied in 2026, still waiting for a decisionWho can move it: West Lindsey Council · planning ref WL/2026/00180
Stow Park Farm, Stow Park - Solar PanelsLuminous Energy Group Solar 35 MW13,000 homes Waiting 2.2 years for a planning decisionWho can move it: West Lindsey Council · planning ref WL/2024/00395
South Carlton - Solar PanelsEnviromena Solar 29 MW11,000 homes Waiting 12 months for a planning decisionWho can move it: West Lindsey Council · planning ref WL/2025/00737
West Burton Solar ProjectIsland Green Power Battery 20 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref EN010132
Highgate Lane, Normanby-By-Spital - Solar Photovoltaic FarmBoultbee Brooks Renewables Walkford Moor Limited Solar 11 MW4,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref WL/2024/00415
Marton Sewage Works, High Street - Battery Energy StorageLoire Capital Holdings Limited Battery 10 MW Applied in 2026, still waiting for a decisionWho can move it: West Lindsey Council · planning ref WL/2026/00169

Plus 2 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Gainsborough 583 MW48 MWnot visible
Sleaford and North Hykeham 43 MW59 MWnot visible
Lincoln 0 MW0 MWnot visible
Brigg and Immingham 96 MW48 MWnot visible
Scunthorpe 165 MW71 MWnot visible
Louth and Horncastle 15 MW96 MWnot visible

Gainsborough has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.