CONSTITUENCY BRIEFING · ENERGYMAP.APP

Caithness, Sutherland and Easter Ross

MP: Jamie Stone (Liberal Democrat) Scotland Data to July 2026

Caithness, Sutherland and Easter Ross was paid £36m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for about 1.2 years. A further 938 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 819,000 homes. A 300 MW battery approved at Philips Mains, Mey in 2026 would store power that is currently wasted; it has not been built.

Ranks 1 of 650 for clean power approved and not built; 2 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Titan Battery StorageGreen Switch Capital Limited Battery 500 MW Applied in 2025, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005199
Philips Mains, Mey - Battery Energy StorageAmpeak Energy Battery 300 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004838
Spittal Mains, Spittal - Battery Energy Storage SystemField Spittal Limited Battery 300 MW Waiting 19 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005116
Upper Bighouse Biomass BoilersUpper Bighouse Farm Biomass (dedicated) 260 MW Waiting 5.5 years for a planning decisionWho can move it: Highland Council · planning ref 21/00334/FUL
Invershin Community Hall - Wind Farm & Battery StorageGarvary Wind Farm Limited Onshore wind 222 MW194,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003251
Strathy SouthScottish and Southern Energy (SSE) Onshore wind 208 MW182,000 homes Cannot connect to the grid until 2027, 9 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2027 · planning ref EC00003113
Inveroykel Wind FarmRWE Renewables UK Swindon Limited Onshore wind 191 MW167,000 homes Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO) · earliest connection 2031 · planning ref ECU00005210
Achies - Battery Energy Storage SystemSun4net Limited Battery 162 MW Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2037 · planning ref ECU00006111
Ballach Wind FarmEnergiekontor (UK) Limited Onshore wind 144 MW126,000 homes Cannot connect to the grid until 2037Who can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2037 · planning ref ECU00005219
Coille Linne Wind Farm- Wind TurbinesEnergiekontor (UK) Limited Onshore wind 108 MW95,000 homes Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2037 · planning ref ECU00005163
Shinness Wind FarmShinness Wind Farm Limited Onshore wind 106 MW92,000 homes Waiting 2.3 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004597
Shinness Wind FarmShinness Wind Farm Limited Battery 105 MW Waiting 2.3 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004597

Plus 75 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Caithness, Sutherland and Easter Ross 938 MW1,306 MW£36m
Inverness, Skye and West Ross-shire 453 MW1,272 MW£41m

Caithness, Sutherland and Easter Ross has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.