Caithness, Sutherland and Easter Ross
Caithness, Sutherland and Easter Ross was paid £36m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for about 1.2 years. A further 938 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 819,000 homes. A 300 MW battery approved at Philips Mains, Mey in 2026 would store power that is currently wasted; it has not been built.
Ranks 1 of 650 for clean power approved and not built; 2 of 19 among seats with visible switch-off payments.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Titan Battery StorageGreen Switch Capital Limited | Battery | 500 MW | Applied in 2025, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005199 |
| Philips Mains, Mey - Battery Energy StorageAmpeak Energy | Battery | 300 MW | Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004838 |
| Spittal Mains, Spittal - Battery Energy Storage SystemField Spittal Limited | Battery | 300 MW | Waiting 19 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005116 |
| Upper Bighouse Biomass BoilersUpper Bighouse Farm | Biomass (dedicated) | 260 MW | Waiting 5.5 years for a planning decisionWho can move it: Highland Council · planning ref 21/00334/FUL |
| Invershin Community Hall - Wind Farm & Battery StorageGarvary Wind Farm Limited | Onshore wind | 222 MW194,000 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003251 |
| Strathy SouthScottish and Southern Energy (SSE) | Onshore wind | 208 MW182,000 homes | Cannot connect to the grid until 2027, 9 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2027 · planning ref EC00003113 |
| Inveroykel Wind FarmRWE Renewables UK Swindon Limited | Onshore wind | 191 MW167,000 homes | Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO) · earliest connection 2031 · planning ref ECU00005210 |
| Achies - Battery Energy Storage SystemSun4net Limited | Battery | 162 MW | Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2037 · planning ref ECU00006111 |
| Ballach Wind FarmEnergiekontor (UK) Limited | Onshore wind | 144 MW126,000 homes | Cannot connect to the grid until 2037Who can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2037 · planning ref ECU00005219 |
| Coille Linne Wind Farm- Wind TurbinesEnergiekontor (UK) Limited | Onshore wind | 108 MW95,000 homes | Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2037 · planning ref ECU00005163 |
| Shinness Wind FarmShinness Wind Farm Limited | Onshore wind | 106 MW92,000 homes | Waiting 2.3 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004597 |
| Shinness Wind FarmShinness Wind Farm Limited | Battery | 105 MW | Waiting 2.3 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004597 |
Plus 75 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Caithness, Sutherland and Easter Ross | 938 MW | 1,306 MW | £36m |
| Inverness, Skye and West Ross-shire | 453 MW | 1,272 MW | £41m |
Caithness, Sutherland and Easter Ross has more approved-and-waiting capacity than any of its neighbouring seats.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call