Berwickshire, Roxburgh and Selkirk
Berwickshire, Roxburgh and Selkirk was paid £7.0m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 85 days. A further 85 MW of approved clean power (mostly onshore wind) is still waiting to be built here: enough to supply a year's electricity to 64,000 homes. A 50 MW battery approved at Keepers House, Byrecleugh in 2025 would store power that is currently wasted; it has not been built.
Ranks 75 of 650 for clean power approved and not built; 8 of 19 among seats with visible switch-off payments.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Eccles II Substation - Battery Energy Storage SystemMatrix Renewables | Battery | 500 MW | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00004804 |
| Eccles Battery Energy Storage SystemZenobe Energy Limited | Battery | 400 MW | Cannot connect to the grid until 2026, 3 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2026 · planning ref ECU00004601 |
| Teviot Wind FarmMuirhall Energy Limited | Onshore wind | 350 MW306,000 homes | Waiting 4.2 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00003249 |
| Pittlesheugh Farm Bess, Springwells Farmhouse - Battery Energy StorageThe Energy Workshop | Battery | 340 MW | Waiting 2.3 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004872 |
| Bowshiel Farm - Solar FarmVoltalia UK | Solar | 165 MW60,000 homes | Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005085 |
| Bishops Dal - Battery Energy Storage SystemRenewable Energy Systems RES Limited (Beaufort) | Battery | 150 MW | Waiting 17 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2030 · planning ref ECU00005049 |
| Longcroft Wind FarmRenewable Energy Systems | Onshore wind | 125 MW110,000 homes | Waiting 2.8 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004774 |
| Dunside Wind FarmEDF Energy | Onshore wind | 108 MW94,000 homes | Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003436 |
| Teviot Wind FarmMuirhall Energy Limited | Battery | 100 MW | Waiting 4.2 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00003249 |
| Mid Hill Wind FarmInvenergy Services UK | Onshore wind | 94 MW82,000 homes | Applied in 2025, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005192 |
| Bowshiel Farm - Battery Energy StorageVoltalia UK | Battery | 80 MW | Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005085 |
| Chesters - Millmoor Rig Wind Farm & Battery Energy StorageESB Asset Development UK Ltd | Onshore wind | 78 MW68,000 homes | Waiting 3.7 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00003426 |
Plus 25 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Berwickshire, Roxburgh and Selkirk | 85 MW | 685 MW | £7.0m |
| Hexham | 23 MW | 56 MW | not visible |
| Dumfriesshire, Clydesdale and Tweeddale | 913 MW | 1,451 MW | £15m |
| Midlothian | 4.2 MW | 0 MW | not visible |
| Carlisle | 70 MW | 49 MW | not visible |
| Lothian East | 0.4 MW | 216 MW | £3.2m |
Dumfriesshire, Clydesdale and Tweeddale next door has 913 MW waiting, more than Berwickshire, Roxburgh and Selkirk's 85 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call