CONSTITUENCY BRIEFING · ENERGYMAP.APP

Berwickshire, Roxburgh and Selkirk

MP: John Lamont (Conservative) Scotland Data to July 2026

Berwickshire, Roxburgh and Selkirk was paid £7.0m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 85 days. A further 85 MW of approved clean power (mostly onshore wind) is still waiting to be built here: enough to supply a year's electricity to 64,000 homes. A 50 MW battery approved at Keepers House, Byrecleugh in 2025 would store power that is currently wasted; it has not been built.

Ranks 75 of 650 for clean power approved and not built; 8 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Eccles II Substation - Battery Energy Storage SystemMatrix Renewables Battery 500 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00004804
Eccles Battery Energy Storage SystemZenobe Energy Limited Battery 400 MW Cannot connect to the grid until 2026, 3 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2026 · planning ref ECU00004601
Teviot Wind FarmMuirhall Energy Limited Onshore wind 350 MW306,000 homes Waiting 4.2 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00003249
Pittlesheugh Farm Bess, Springwells Farmhouse - Battery Energy StorageThe Energy Workshop Battery 340 MW Waiting 2.3 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004872
Bowshiel Farm - Solar FarmVoltalia UK Solar 165 MW60,000 homes Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005085
Bishops Dal - Battery Energy Storage SystemRenewable Energy Systems RES Limited (Beaufort) Battery 150 MW Waiting 17 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2030 · planning ref ECU00005049
Longcroft Wind FarmRenewable Energy Systems Onshore wind 125 MW110,000 homes Waiting 2.8 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004774
Dunside Wind FarmEDF Energy Onshore wind 108 MW94,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003436
Teviot Wind FarmMuirhall Energy Limited Battery 100 MW Waiting 4.2 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00003249
Mid Hill Wind FarmInvenergy Services UK Onshore wind 94 MW82,000 homes Applied in 2025, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005192
Bowshiel Farm - Battery Energy StorageVoltalia UK Battery 80 MW Waiting 14 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005085
Chesters - Millmoor Rig Wind Farm & Battery Energy StorageESB Asset Development UK Ltd Onshore wind 78 MW68,000 homes Waiting 3.7 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00003426

Plus 25 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Berwickshire, Roxburgh and Selkirk 85 MW685 MW£7.0m
Hexham 23 MW56 MWnot visible
Dumfriesshire, Clydesdale and Tweeddale 913 MW1,451 MW£15m
Midlothian 4.2 MW0 MWnot visible
Carlisle 70 MW49 MWnot visible
Lothian East 0.4 MW216 MW£3.2m

Dumfriesshire, Clydesdale and Tweeddale next door has 913 MW waiting, more than Berwickshire, Roxburgh and Selkirk's 85 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call