North West Essex

MP: Mrs Kemi Badenoch (Conservative) England Data to July 2026

North West Essex has 623 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 226,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,575 homes.

Ranks 5 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
LongfieldLongfield Solar Energy Farm Limited (part of EDF Renwables) Solar 500 MW182,000 homes Cannot connect to the grid until 2028, 5 years after it was approvedWho can move it: the grid operator (NESO) and National Grid · earliest connection 2028 · planning ref EN010118
Berden Hall Solar FarmBritish Solar Renewables Solar 56 MW20,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref UTT/22/2046/PINS
Maggots End Road, Berden - Solar Farm & Battery StorageLow Carbon Limited Solar 50 MW18,000 homes Refused by Uttlesford Council in 2026Who can move it: Uttlesford Council · planning ref UTT/25/1224/FUL
Thaxted - Solar farmLow Carbon Limited Solar 40 MW15,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref UTT/21/1833/FUL
Parsonage Farm - Solar PV Farm & Battery StorageTrilogy Logistics REIT Limited Solar 30 MW11,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref UTT/25/1742/FUL
Wickham Hall Estate Solar Photovoltaic FarmEndurance Energy Wickham Hall Limited Solar 20 MW7,300 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref UTT/24/1417/PINS
Stanstead Solar ProjectManchester Airport Group Plc Solar 14 MW5,200 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref S62A/22/0000004
Merks Hill Farm, Braintree Road - Solar FarmSky UK Development Limited Solar 12 MW4,400 homes Waiting 14 months for a planning decisionWho can move it: Uttlesford Council · planning ref UTT/25/1374/FUL
Wickham Hall Estate - Battery StorageEndurance Energy Wickham Hall Limited Battery 10 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref UTT/24/1417/PINS
Dunmow Solar Farm, Chelmsford Road - Solar FarmDunmow Solar Limited Solar 9.9 MW3,600 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref UTT/23/2136/FUL

Plus 1 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
North West Essex 623 MW68 MWnot visible
Brentwood and Ongar 1 MW50 MWnot visible
Maldon 139 MW63 MWnot visible
Chelmsford 0.2 MW0 MWnot visible
Harlow 56 MW0 MWnot visible
Witham 24 MW193 MWnot visible

North West Essex has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.