Stone, Great Wyrley and Penkridge

MP: Sir Gavin Williamson (Conservative) England Data to July 2026

Stone, Great Wyrley and Penkridge has 125 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 45,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.5m across the constituency's 38,510 homes.

Ranks 46 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Oaklands Farm, New Road - Battery Energy StorageConrad Energy (Developments) II Limited Battery 70 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/01044/FULM
Levedale Road, Levedale - Battery Energy StorageAnglo Renewables Limited Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00145/FUL
Upper Latherford Farm, Latherford Lane - Battery Energy Storage SystemNet Zero Twelve Limited Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00883/FUL
Preston Hill Farm, Penkridge - Solar FarmEngena Limited Solar 50 MW18,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00009/FUL
Lower Farm, Drointon Lane - Solar farm & Battery Energy StorageInnova Renewables Solar 50 MW18,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/36938/FUL
Hobble Lane, Great Wyrley - Battery Energy StorageAnglo ES Great Wyrley Limited Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00010/FULM
Hanyards Lane, Tixall - Solar Energy ParkPrivate Developer Solar 50 MW18,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/37621/FUL
Yew Tree Farm, Drointon LanePush Energy Solar 49 MW18,000 homes Waiting 15 months for a planning decisionWho can move it: Stafford Council · planning ref 25/40571/FUL
Lawn Lane, Coven - Solar FarmAnesco Limited Solar 48 MW17,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/01083/FULM
Chillington Estate, Chillington Park - Solar PanelsElgin Energy Esco Limited Solar 40 MW15,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00576/FULM
Chillington Estate, Chillington Park - Battery StorageElgin Energy Esco Limited Battery 40 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00576/FULM
Littywood Farm, Toft Lane - Solar ArrayElgin Energy Services Solar 40 MW15,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/00936/FUL

Plus 4 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Stone, Great Wyrley and Penkridge 125 MW5.8 MWnot visible
Walsall and Bloxwich 1.6 MW0 MWnot visible
Aldridge-Brownhills 0.5 MW0 MWnot visible
Wolverhampton North East 8.1 MW0 MWnot visible
Cannock Chase 0 MW0 MWnot visible
Kingswinford and South Staffordshire 2.5 MW11 MWnot visible

Stone, Great Wyrley and Penkridge has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.