CONSTITUENCY BRIEFING · ENERGYMAP.APP

Orkney and Shetland

MP: Mr Alistair Carmichael (Liberal Democrat) Scotland Data to July 2026

Orkney and Shetland was paid £15m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for about 1.1 years. A further 333 MW of approved clean power (all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 291,000 homes. A 15 MW battery approved at Luggies Knowe, Hill Of Gremista in 2025 would store power that is currently wasted; it has not been built.

Ranks 12 of 650 for clean power approved and not built; 6 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Energy Isles Wind FarmEnergy Isles / Stratcraft Onshore wind 126 MW110,000 homes Cannot connect to the grid until 2032, 9 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2032 · planning ref ECU00001844
Shetland Battery Energy Storage SystemZenobe Energy Battery 70 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00004881
Beaw Field Wind FarmPeel Wind Farms Onshore wind 60 MW52,000 homes Cannot connect to the grid until 2032, 15 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2032 · planning ref EC00003121
Mossy HillPeel Wind Farms (Peel Energy) Onshore wind 47 MW41,000 homes Cannot connect to the grid until 2028, 9 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2028 · planning ref 2018/186/PPF
Orkney’s Community Wind Farm Project - FarayOrkney Islands Council Onshore wind 29 MW25,000 homes Waiting 5.1 years for a planning decisionWho can move it: Orkney Islands Council · earliest connection 2030 · planning ref 21/240/TPPMAJ
Orkney’s Community Wind Farm Project - HoyOrkney Islands Council Onshore wind 29 MW25,000 homes Cannot connect to the grid until 2028, 7 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2028 · planning ref 20/313/TPPMAJ
Orkney’s Community Wind Farm Project - QanternessOrkney Islands Council Onshore wind 29 MW25,000 homes Cannot connect to the grid until 2028, 7 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2028 · planning ref 20/037/TPPMAJ
Nitshill Wind Farm, Hundland HillNisthill Wind Farm Limited Onshore wind 26 MW23,000 homes Waiting 3.9 years for a planning decisionWho can move it: Orkney Islands Council · planning ref 22/320/TPPMAJ
Greentoft, Neven Point, Eday - Wind Turbines & BESSGreen Power (International) Limited Onshore wind 24 MW21,000 homes Waiting 13 months for a planning decisionWho can move it: Orkney Islands Council · planning ref 25/203/TPPMAJ
Hesta Head Wind FarmHoolan Energy/ Hesta Head Wind Farm Onshore wind 20 MW18,000 homes Cannot connect to the grid until 2029, 10 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2029 · planning ref 17/083/TPPMAJ
Costa Head Wind FarmHoolan Energy Onshore wind 16 MW14,000 homes Cannot connect to the grid until 2029, 10 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2029 · planning ref 16/580/TPPMAJ
Luggies Knowe, Hill Of Gremista - Wind Turbines & Battery StorageShetland Aerogenerators Ltd Battery 15 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2024/006/PPF

Plus 8 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Orkney and Shetland 333 MW493 MW£15m
Caithness, Sutherland and Easter Ross 938 MW1,306 MW£36m
Aberdeenshire North and Moray East 215 MW122 MWnot visible
Gordon and Buchan 107 MW187 MW£120k

Caithness, Sutherland and Easter Ross next door has 938 MW waiting, more than Orkney and Shetland's 333 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.