Orkney and Shetland
Orkney and Shetland was paid £15m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for about 1.1 years. A further 333 MW of approved clean power (all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 291,000 homes. A 15 MW battery approved at Luggies Knowe, Hill Of Gremista in 2025 would store power that is currently wasted; it has not been built.
Ranks 12 of 650 for clean power approved and not built; 6 of 19 among seats with visible switch-off payments.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Energy Isles Wind FarmEnergy Isles / Stratcraft | Onshore wind | 126 MW110,000 homes | Cannot connect to the grid until 2032, 9 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2032 · planning ref ECU00001844 |
| Shetland Battery Energy Storage SystemZenobe Energy | Battery | 70 MW | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00004881 |
| Beaw Field Wind FarmPeel Wind Farms | Onshore wind | 60 MW52,000 homes | Cannot connect to the grid until 2032, 15 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2032 · planning ref EC00003121 |
| Mossy HillPeel Wind Farms (Peel Energy) | Onshore wind | 47 MW41,000 homes | Cannot connect to the grid until 2028, 9 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2028 · planning ref 2018/186/PPF |
| Orkney’s Community Wind Farm Project - FarayOrkney Islands Council | Onshore wind | 29 MW25,000 homes | Waiting 5.1 years for a planning decisionWho can move it: Orkney Islands Council · earliest connection 2030 · planning ref 21/240/TPPMAJ |
| Orkney’s Community Wind Farm Project - HoyOrkney Islands Council | Onshore wind | 29 MW25,000 homes | Cannot connect to the grid until 2028, 7 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2028 · planning ref 20/313/TPPMAJ |
| Orkney’s Community Wind Farm Project - QanternessOrkney Islands Council | Onshore wind | 29 MW25,000 homes | Cannot connect to the grid until 2028, 7 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2028 · planning ref 20/037/TPPMAJ |
| Nitshill Wind Farm, Hundland HillNisthill Wind Farm Limited | Onshore wind | 26 MW23,000 homes | Waiting 3.9 years for a planning decisionWho can move it: Orkney Islands Council · planning ref 22/320/TPPMAJ |
| Greentoft, Neven Point, Eday - Wind Turbines & BESSGreen Power (International) Limited | Onshore wind | 24 MW21,000 homes | Waiting 13 months for a planning decisionWho can move it: Orkney Islands Council · planning ref 25/203/TPPMAJ |
| Hesta Head Wind FarmHoolan Energy/ Hesta Head Wind Farm | Onshore wind | 20 MW18,000 homes | Cannot connect to the grid until 2029, 10 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2029 · planning ref 17/083/TPPMAJ |
| Costa Head Wind FarmHoolan Energy | Onshore wind | 16 MW14,000 homes | Cannot connect to the grid until 2029, 10 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2029 · planning ref 16/580/TPPMAJ |
| Luggies Knowe, Hill Of Gremista - Wind Turbines & Battery StorageShetland Aerogenerators Ltd | Battery | 15 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2024/006/PPF |
Plus 8 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Orkney and Shetland | 333 MW | 493 MW | £15m |
| Caithness, Sutherland and Easter Ross | 938 MW | 1,306 MW | £36m |
| Aberdeenshire North and Moray East | 215 MW | 122 MW | not visible |
| Gordon and Buchan | 107 MW | 187 MW | £120k |
Caithness, Sutherland and Easter Ross next door has 938 MW waiting, more than Orkney and Shetland's 333 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call