Carlisle

MP: Ms Julie Minns (Labour) England Data to July 2026

Carlisle has 70 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 25,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.4m across the constituency's 47,449 homes. There is also 44 MW of wind running here on the local network. If that gets switched off, no national record shows it. A 340 MW battery was refused planning here in 2026; while discharging it could have supplied about 1,191,000 homes.

Ranks 96 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Low Harker Farm, Low Harker - Battery Storage FacilityZenobe Energy Limited Battery 400 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/0093
Blackdyke Farm, Blackford - Battery StorageInnova Renewables Battery 400 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/0444
Harker Moss - Battery Energy Storage SystemESB (Harker) Limited Battery 360 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/0680
Blackdyke Farm, Blackford - Battery StorageNovus Renewable Services Limited / Story Construction Battery 340 MW Refused by Cumberland Council in 2026Who can move it: Cumberland Council · planning ref 23/0659
Todhills and Westlinton - Harker Battery Energy Storage FacilityWindel Energy Battery 200 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/0833
Leaps Rigg - Solar FarmOpdenergy UK 7 Limited Solar 50 MW18,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/0415
High Parkfoot FarmElgin Energy Solar 20 MW7,300 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 18/0197
Grassing Rome Street - Battery StorageSTOR 141 Limited Battery 16 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/0513

Plus 2 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Carlisle 70 MW49 MWnot visible
Hexham 23 MW56 MWnot visible
Penrith and Solway 4.7 MW92 MWnot visible
Dumfriesshire, Clydesdale and Tweeddale 913 MW1,451 MW£15m
Berwickshire, Roxburgh and Selkirk 85 MW685 MW£7.0m

Dumfriesshire, Clydesdale and Tweeddale next door has 913 MW waiting, more than Carlisle's 70 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.