How every number
is worked out

Written for a sceptical energy analyst. Every source is open and credential-free; every transformation is in the published data; the reconciliation against NESO is below, warts included.

What is original here, and what is not

None of the underlying data is ours and none of it is secret. Elexon publishes every balancing action, DESNZ publishes the planning database, NESO publishes the constraint costs and the connection queue, ONS publishes the boundaries and the census. Anyone can download all of it. If you already work in energy, you have seen these sources.

What did not exist before, as far as we can tell, is the join:

So: the facts are public, the arrangement is the work. If you think a join is wrong, the mapping file, the reconciliation and every seat's JSON are published so you can check it rather than take our word for it. Corrections are welcome and get credited.

Number 1 — £ paid to switch off wind farms (the industry word is "curtailment")

Source: the Elexon settlement bid stack (/balancing/settlement/stack/all/bid), which gives the accepted bid volume (MWh) and original bid price (£/MWh) per balancing-mechanism unit (BMU) per half-hour, as derived by Elexon settlement. We keep turn-down (bid) actions on wind BMUs only. Cost = volume × price: a wind farm bidding a negative price is paid to reduce output, so the product is a positive cost to the system.

Attribution: BMUs are matched to sites in the government's Renewable Energy Planning Database (REPD) by a hand-reviewed mapping file with a confidence grade per row (candidate suggestions are published too). One site can span several BMUs (Viking has four) and one BMU can span several REPD entries (phased builds — the share column splits them). Sites are placed in constituencies by point-in-polygon against the ONS July-2024 boundaries.

What is deliberately left out of seat totals: offshore wind (£210m in the window) is reported nationally, never attributed to a coastal seat. Money on BMUs we could not confidently map — £21m, 5.2% of the total — sits in a published unattributed bucket rather than being guessed into a seat. Corrections to the mapping are welcome.

Window: 1 August 2025 to 31 July 2026. Elexon revises settlement data for months; the weekly rebuild re-pulls the trailing 14 days.

Reconciliation against NESO

NESO publishes no wind-only curtailment cost in any machine-readable dataset, so the primary check is volumes, against NESO's per-BMU "Wind BOA Volumes" dataset, plus the GWh figures NESO quotes in its Monthly Balancing Cost Report. One unit note: NESO's BOA_Volume column is MW per half-hour settlement period, so energy = value × 0.5 — uncorrected it reads exactly double.

MonthOurs (GWh)NESO (GWh)Ratio
2025-088128111.002
2025-091,0841,0821.002
2025-101,2941,2931.000
2025-119619581.003
2025-121,0091,0041.005
2026-011,2321,2311.000
2026-028648641.000
2026-031,3651,3631.001

Spot checks against the report itself: May 2026 — ours 591 GWh vs NESO's quoted 591; June 2026 — ours 707 vs quoted 709. Per-BMU, 51 units above 20 GWh were compared; 1 fall outside ±2% and are listed in reconciliation.json. The build fails if any complete month disagrees by more than 2%.

Number 2 — consented but not built

Source: REPD quarterly extract (DESNZ), July 2026 edition. "Stuck" means development status Awaiting Construction or Under Construction with consent granted more than 24 months before the extract date (a 12-month cut is also computed and published). Consent date is the latest of planning permission granted, appeal granted, or Secretary of State granted. Refusals, withdrawals and the median months from application to decision use a five-year window.

What counts as "clean power" here: onshore and offshore wind, solar, hydro, tidal and wave — the generating technologies in the planning database. Battery storage is counted separately throughout this site, because a battery does not generate electricity; it moves it in time. Every seat page and briefing names the technology mix rather than leaving "clean power" to the imagination.

A note on "enough for X homes". Electricity does not flow from a particular project to particular houses. Everything generated goes into the national grid, and every home draws from that shared pool — so a wind farm in Caithness is not "powering" Caithness, and a solar farm outside a town does not supply that town. The homes figure is a way of sizing an amount of electricity in units people recognise: it is the annual output of the project divided by what a typical household uses in a year. It is a measure of quantity, not of who receives it.

Homes-equivalent = MW × technology load factor (DUKES 2026, five-year average) × 8,760 h ÷ 2,500 kWh (Ofgem's typical household electricity consumption, cut from 2,700 to 2,500 kWh in July 2026 — a change that quietly moved every homes-equivalent claim on the internet). REPD only includes projects above 150 kW (1 MW before 2021), understating small-scale totals. Statuses lag: where a "stuck" site demonstrably has a generating BMU we say so in the mapping notes.

Number 3 — the constraint bill per household

Source: NESO's Monthly Balancing Services Summary, constraints definition (England & Wales + Cheviot + Scotland constraint actions, constraint ancillary services, RoCoF/inertia, constrained sterilised headroom), cross-filled from the daily Constraint Breakdown dataset for months MBSS has not yet covered. Rolling 12 months: £2.5bn ÷ 27,292,462 GB households (Census 2021/22 via ONS, NRS and NISRA) = £92 per household. It is a national figure — the same for every GB seat; only the seat total varies with household count. Northern Ireland is in the all-Ireland SEM and is shown as not applicable, not as zero.

Relationship between the numbers: paying wind farms to switch off (£409m) is 16% of the whole constraint bill. The rest is mostly the mirror image — paying generators south of the bottleneck to turn up — plus voltage and stability actions. Number 1 is what was paid to wind here; Number 3 is the whole system bill.

Batteries

Battery figures come from the same planning database (REPD), Technology Type = Battery, bucketed as operating / being built / approved-not-built / refused (five-year window) / in planning. REPD carries no MWh (duration) column, so we never claim hours of storage. REPD's operating figure (5.0 GW) lags reality — industry trackers put the fleet at about 7.2 GW — so treat the operating number as a floor; the approved and refused numbers are planning records and are not affected by that lag.

The B6 bottleneck figures

The "wires are full" numbers on the front page come from NESO's day-ahead constraint flows and limits dataset for the SCOTEX (B6, Scotland–England) boundary: the flow is NESO's day-ahead modelled unconstrained flow — what wanted to cross — not metered outturn, because NESO publishes no outturn boundary flows. "Full" means wanted flow at or above the boundary limit.

Planning statuses: what we claim, and how to check it

Every planning status on this site — approved, refused, under construction, awaiting a decision — comes from one place: the Renewable Energy Planning Database (REPD), the quarterly extract published by the Department for Energy Security and Net Zero. We do not visit council websites or interpret committee papers. That has three consequences a careful reader should know:

If we cannot check a claim, we do not publish it. Two rules follow from that:

Where the council records come from. There is no national planning register — every council keeps its own — so both the refusal check and the reference links go through PlanIt, a free service that collects council registers and publishes them in a machine-readable form. It is an aggregator, not the source: each record it returns carries a link back to the deciding council's own register, and that is the one that settles any disagreement with us.

One further caution about searching for these projects yourself: battery and solar applications are often named after a farm or field rather than the nearest town, and several similar schemes can sit within a few miles of each other. A refusal you find in the news is not necessarily the refusal in our table. The application reference is the only reliable way to tell two neighbouring schemes apart.

Why a project is stuck, and what building it would do

Each project in a constituency briefing gets one reason, assigned by an ordered rule set — refused, then under appeal, then awaiting a planning decision past 12 months, then connections-reform outcome, then grid connection date, then under construction, then approved with no recorded progress, then in planning. First match wins; all matches are kept in the seat JSON. Where the public record does not say, the reason is "no public record of what is holding this up" — we never guess. "Who can move it" follows from the reason: the named planning authority, the Planning Inspectorate, NESO and the network owner, or the developer.

How we decide who can move a project

Each project's "who can move it" follows mechanically from the reason it is stuck. We do not judge who is at fault; we name the organisation that holds the next decision:

What is holding it upWho can move itWhy that organisation
RefusedThe council that refused it, named from the planning databaseIt made the decision. A refused scheme moves by being appealed, or by a fresh application that answers the reasons.
Refused on appealThe planning appeal inspectorThe appeal has already been determined by the Planning Inspectorate, not the council.
Waiting for a planning decisionThe council handling the applicationOnly the authority determining it can issue a decision.
Cannot connect until a future yearThe grid operator (NESO) and the network owner named in the connection registerThe connection date sits in NESO's queue and the relevant transmission owner's works, not with the council or the developer.
Still in the grid queue reviewThe grid operator (NESO)NESO runs the queue reform that will set the project's date.
Approved, nothing has happened sinceThe developer and the network companyPlanning permission is in hand and no public record shows an external blocker, so the next move is commercial: financing, ordering equipment, agreeing the connection.
Under constructionThe developerNothing is blocking it; it is being built.

Two honest limits. First, "the developer and the network company" is the weakest of these: it means only that no public record shows anyone else holding the project up, which is not the same as knowing why it has not been built — the reason may be a supply chain, a landowner, or a decision never to proceed. Second, where a council is named, we name the authority and never an individual officer or councillor; the decision is the council's, and the reasons for it are in its own register rather than here.

Why "nothing has happened since" is the commonest answer. It applies to a little over half the projects on this site, and that is a fact about the public record rather than about the projects. The planning database tracks a project through the planning system and then stops: it records the date permission was granted, and the date construction started, and nothing in between. There is no public field for ordering a transformer, signing a connection agreement, reaching financial close, or quietly shelving a scheme. So for a project that holds permission and has not started work, the honest statement is that no public record shows anyone else holding it up — not that we know it is stalled, and not that we know why. Where a grid connection date exists in NESO's register we say so, because that is the one post-permission milestone anybody publishes. The rest of the consent stack — land rights, finance, a buyer for the power — is set out under every approval a project needs, and most of it is private.

Every approval a project needs

Planning permission is one gate of several, and it is the one everybody reports on because it is the one that holds a public hearing. A project can hold it and still be years from being built. This is the full stack, who grants each part, and — the point of the table — whether a member of the public can check it at all. Researched and every source fetched on 25 August 2026.

ApprovalGranted byWhen it appliesCan the public see it?How we know
Planning permission The local council Always Yes — the council's planning register Section 69, Town and Country Planning Act 1990; article 40, Town and Country Planning (Development Management Procedure) (England) Order 2015
Environmental assessment decision The local council any site over half a hectare Yes — the council's planning register, filed alongside the application Schedule 2, paragraph 3(a), Town and Country Planning (Environmental Impact Assessment) Regulations 2017 — threshold 0.5 hectare
Grid connection agreement The network company (NESO for the national grid, or the regional network operator) Always Partly — the connection registers show the size, the status and the date, but never the terms NESO Transmission Entry Capacity register (16 fields, checked 2026-08-25) and the regional Embedded Capacity Registers
Generation licence Ofgem only above 50 MW Yes — Ofgem's public register Class A exemption, Schedule 2, Electricity (Class Exemptions from the Requirement for a Licence) Order 2001
Scottish Ministers' consent The Scottish Government Scotland only, above 50 MW Yes — the Energy Consents Unit register Section 36, Electricity Act 1989. Batteries are still generating stations in Scotland: the 2020 orders that took them out of the national regime cover England and Wales only
Development consent order The Secretary of State, on the Planning Inspectorate's recommendation England, solar over 100 MW Yes — the national infrastructure planning register Infrastructure Planning (Onshore Wind and Solar Generation) Order 2025, which raised the solar threshold from 50 MW to 100 MW on 31 December 2025. Standalone batteries were taken out of this regime in 2020 and are decided by the council at any size
Rights over the land The landowner Always No — the rent, the length of the lease and what happens at the end are private between the developer and the landowner Land Registry titles can show that a long lease exists, but never its terms, and there is no free bulk route to them — a title costs £3 a time
Money and a buyer for the power Lenders, investors and whoever buys the electricity Always No — never published Companies House charges name a project's secured lenders, free and to anyone, but never the price or the conditions. The Capacity Market register would name anyone holding security over a project; it sits behind a sign-in (emrdeliverybody.com, checked 2026-08-26), so it is not a source a reader can follow

Two rows have no national register to link, because there is no such thing: planning permission and the environmental assessment decision sit on each council's own register, one register per council. Where a project on this site holds a reference we have checked against that register, the reference on its seat page links straight to the record. Every URL in the table was last fetched, and answered, on 26 August 2026; the machine-readable version is consents.json.

What a project does not need

Three approvals get assumed onto lists like this one and do not normally apply. Showing them as missing would invent a problem a project does not have, so we name them here instead.

Connection dates come from NESO's Transmission Entry Capacity register and its Embedded register — the public queue of projects with agreed connection dates. NESO repeats rows per project stage, so we deduplicate on Project ID, keeping the earliest connection date. The registers carry no postcode or grid reference, so the join to the planning database is by normalised project name plus a capacity check, published as a mapping file with confidence grades and a candidate list. A guard rejects matches that rest only on a shared generic phrase — "Greener Grid Park" appears in many project names and is not evidence that two records are the same project. We would rather miss a match than assert a wrong one, so a project with no confident match simply shows its planning status instead of a connection date.

Connections reform (Gate 2). NESO does not publish project-level reform outcomes: its detailed results are aggregated by zone for commercial-sensitivity reasons. The machine-readable outcome is the Gate column added to the connection registers in November 2025, populated only as agreements are countersigned — so most of the queue is still blank, and a project without a Gate marking has not necessarily failed anything.

Impact estimates come from per-MW factors in a versioned file, each with a source, a date and a status. A sentence only appears when the factor for that technology exists — a missing factor means a missing sentence, never a zero. Three distinctions we keep visible, because they are where this kind of estimate usually goes wrong:

FactorTechnologyValueStatusAs of
Community benefit fundOnshore wind£5,000/MW/yrpublished guidance2025-07-04
Business ratesOnshore wind£17,900/MW/yrderived from VOA rating list2026-02-10
Peak construction workersOnshore wind1.6–1.9 per MWpublished guidance2024-05-13
Community benefit fundSolar£850/MW/yrproposed, not in force2026-02-18
Business ratesSolar£1,330/MW/yrderived from VOA rating list2026-02-10
Peak construction workersSolar0.7–1.15 per MWpublished guidance2023-11-01
Community benefit fundBattery£150/MW/yrproposed, not in force2026-02-18
Business ratesBattery£3,180/MW/yrderived from VOA rating list2026-08-03

What we cannot see

Comparators

Every tangible framing resolves through a versioned comparators file; nothing is hardcoded. Values, sources and as-of dates:

ComparatorValueSourceAs of
tdcv electricity kwh2,500Ofgem Typical Domestic Consumption Values, medium electricity profile (Profile Class 1)2026-07-01
unit rate gbp per kwh0.2611Ofgem price cap Jul-Sep 2026, electricity single-rate direct-debit unit price including VAT (standing charge 57.19p/day excluded)2026-07-01
capacity factor onshore wind0.2496DUKES 2026 Table 6.3, mean of annual load factors 2021-2025, onshore wind (average-capacity basis)2026-07-30
capacity factor offshore wind0.3813DUKES 2026 Table 6.3, mean of annual load factors 2021-2025, offshore wind (average-capacity basis)2026-07-30
capacity factor solar pv0.1036DUKES 2026 Table 6.3, mean of annual load factors 2021-2025, solar PV (average-capacity basis)2026-07-30
capacity factor hydro0.3279DUKES 2026 Table 6.3, mean of annual load factors 2021-2025, natural-flow hydro (average-capacity basis)2026-07-30