Dumfriesshire, Clydesdale and Tweeddale
Dumfriesshire, Clydesdale and Tweeddale was paid £15m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 203 days. A further 913 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 773,000 homes. A 500 MW battery approved at Redshaw Battery Energy Storage in 2025 would store power that is currently wasted; it has not been built. A 200 MW battery was refused planning here in 2026; while discharging it could have supplied about 701,000 homes.
Ranks 2 of 650 for clean power approved and not built; 5 of 19 among seats with visible switch-off payments.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Coalburn II Energy Storage Facility - Battery Storage FacilityAlcemi Storage Development Limited | Battery | 1,000 MW | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00004698 |
| High Netherfauld House Farm 1, Tower Road - Battery Energy Storage SystemESB (Harker) Limited | Battery | 502 MW | Waiting 15 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006063 |
| Redshaw Battery Energy StorageBayWa r.e. UK Limited | Battery | 500 MW | Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO) · earliest connection 2031 · planning ref ECU00005122 |
| Gretna Green Battery StorageGresham House Devco Pipeline | Battery | 456 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004986 |
| Scoop Hill Wind FarmCommunity Wind Power Limited | Onshore wind | 432 MW378,000 homes | Refused by the Scottish Government (it decides big energy projects) in 2026Who can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00000533 |
| Lagrae Battery Energy Storage SystemBuccleuch Estates Limited | Battery | 400 MW | Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO) · earliest connection 2036 · planning ref ECU00004991 |
| Glenmuckloch Pumped Storage HydroBuccleuch Estates | Pumped Storage Hydroelectricity | 400 MW | Approved 10 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref EC00005236 |
| Red Moss - Battery StorageGreen Switch Capital Limited | Battery | 342 MW | Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO) · earliest connection 2030 · planning ref ECU00005043 |
| Faw Side Community Wind FarmCommunity Windpower | Onshore wind | 315 MW275,000 homes | Refused by the Scottish Government (it decides big energy projects) in 2023Who can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00001833 |
| Sanquhar 2 Community Wind FarmCommunity Windpower | Onshore wind | 308 MW269,000 homes | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00001801 |
| Bodinglee Wind FarmBanks Group | Onshore wind | 266 MW233,000 homes | Waiting 3.1 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004839 |
| Hagshaw Energy Cluster – Western Expansion3R Energy Solutions Limited | Battery | 225 MW | Waiting 15 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · earliest connection 2028 · planning ref ECU00004623 |
Plus 70 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Dumfriesshire, Clydesdale and Tweeddale | 913 MW | 1,451 MW | £15m |
| Midlothian | 4.2 MW | 0 MW | not visible |
| Livingston | 118 MW | 116 MW | not visible |
| Edinburgh South West | 0 MW | 0 MW | not visible |
| Carlisle | 70 MW | 49 MW | not visible |
| Berwickshire, Roxburgh and Selkirk | 85 MW | 685 MW | £7.0m |
Dumfriesshire, Clydesdale and Tweeddale has more approved-and-waiting capacity than any of its neighbouring seats.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call