CONSTITUENCY BRIEFING · ENERGYMAP.APP

Burnley

MP: Oliver Ryan (Labour (Co-op)) England Data to July 2026

Burnley has 1 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 400 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 45,122 homes. There is also 38 MW of wind running here on the local network. If that gets switched off, no national record shows it. A 100 MW battery was refused planning here in 2025; while discharging it could have supplied about 350,000 homes.

Ranks 416 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
The Old Vicarage, Reedley - Battery StorageEuropean Energy A/S Battery 100 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/0507/FUL
Shuttleworth House, Higher Shuttleworth - Battery Energy Storage SystemRenewable Connections Developments Limited Battery 100 MW Refused by Burnley Council in 2025Who can move it: Burnley Council · planning ref FUL/2025/0344
Padiham - Battery Energy StorageEnergi Generation Limited Battery 100 MW Refused by Burnley Council in 2024Who can move it: Burnley Council · planning ref FUL/2024/0258
Widow Hill, Balderstone Lane - Battery Energy Storage SystemP3P Partners LLP Battery 70 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref FUL/2021/0375
Huncoat Power Station - Battery Storage FacilityNewgen Limited Battery 45 MW Refused by Burnley Council in 2024Who can move it: Burnley Council · planning ref FUL/2023/0785
Coal Clough Wind Farm (Co-located)ScottishPower Renewables Solar 10 MW3,600 homes Waiting 6.9 years for a planning decisionWho can move it: Burnley Council · planning ref FUL/2019/0470

Plus 1 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Burnley 1 MW38 MWnot visible
Calder Valley 1.4 MW12 MWnot visible
Rossendale and Darwen 0.3 MW75 MWnot visible
Hyndburn 12 MW25 MWnot visible
Pendle and Clitheroe 2.4 MW0 MWnot visible

Hyndburn next door has 12 MW waiting, more than Burnley's 1 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.