CONSTITUENCY BRIEFING · ENERGYMAP.APP

Cheadle

MP: Tom Morrison (Liberal Democrat) England Data to July 2026

Cheadle has 1.2 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 400 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.6m across the constituency's 39,132 homes.

Ranks 396 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Woodford Road - Battery Energy Storage SystemPegasus Group Battery 100 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/5075/FUL
Newby Road, Hazel Grove - Battery StorageAMP Energy Services Limited Battery 7.5 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DC/084337

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Cheadle 1.2 MW0 MWnot visible
Macclesfield 1 MW0 MWnot visible
Hazel Grove 0 MW0 MWnot visible
Stockport 1.2 MW0.3 MWnot visible
Tatton 5.2 MW0 MWnot visible
Wythenshawe and Sale East 2.4 MW0 MWnot visible

Tatton next door has 5.2 MW waiting, more than Cheadle's 1.2 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call