Tatton has 5.2 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,900 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,059 homes.
Ranks 259 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Aston Grange, Aston - Solar Panels & Battery Energy Storage SystemInnova Renewables | Solar | 20 MW7,300 homes | Waiting 17 months for a planning decisionWho can move it: Cheshire West and Chester Council · planning ref 25/00100/FULEIA |
| Aston Grange, Aston - Solar Panels & Battery Energy Storage SystemInnova Renewables | Battery | 6 MW | Waiting 17 months for a planning decisionWho can move it: Cheshire West and Chester Council · planning ref 25/00100/FULEIA |
| Wildersmoor Hall Farm, Higher Lane - Solar FarmLymm Community Energy Limited | Solar | 2.5 MW900 homes | Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2024/00087/FULM |
| Barclays Bank Plc, Radbroke Solar Carport - Solar PanelsBarclays Plc | Solar | 2.5 MW900 homes | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 22/0560M |
| Stublach Project Solar FarmStorengy UK Limited | Solar | 2.2 MW800 homes | Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 20/04118/FUL |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Tatton | 5.2 MW | 0 MW | not visible |
| Chester South and Eddisbury | 19 MW | 30 MW | not visible |
| Macclesfield | 1 MW | 0 MW | not visible |
| Cheadle | 1.2 MW | 0 MW | not visible |
| Congleton | 18 MW | 5.4 MW | not visible |
| Mid Cheshire | 23 MW | 0 MW | not visible |
Mid Cheshire next door has 23 MW waiting, more than Tatton's 5.2 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call
Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.