Wythenshawe and Sale East
Wythenshawe and Sale East has 2.4 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 900 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.3m across the constituency's 46,836 homes.
Ranks 320 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Freshfields, Fairy Lane - Battery StorageSTOR Power Utilities Limited | Battery | 100 MW | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 109463/FUL/22 |
| Golf Road - Battery Energy StorageCragside Energy Limited | Battery | 90 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 111105/FUL/23 |
| Sale Golf Club, Golf Road - Battery Storage247 Power Limited | Battery | 70 MW | Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 110666/FUL/23 |
| Sunbank Lane - Solar PanelsIgen Energy Limited | Solar | 4.3 MW1,600 homes | Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 145280/P14J/2026 |
| Sunbank Lane Solar PanelsZestec Asset Management | Solar | 1.5 MW500 homes | Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 130585/FO/2021 |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Wythenshawe and Sale East | 2.4 MW | 0 MW | not visible |
| Cheadle | 1.2 MW | 0 MW | not visible |
| Tatton | 5.2 MW | 0 MW | not visible |
| Altrincham and Sale West | 0.9 MW | 0 MW | not visible |
| Manchester Withington | 2.1 MW | 0 MW | not visible |
| Stretford and Urmston | 1.8 MW | 0 MW | not visible |
Tatton next door has 5.2 MW waiting, more than Wythenshawe and Sale East's 2.4 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call
Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.