CONSTITUENCY BRIEFING · ENERGYMAP.APP
South West Hertfordshire
South West Hertfordshire has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.6m across the constituency's 38,995 homes.
Ranks 455 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Langleybury Film HubRalph Trustees Limited | Solar | 3 MW1,100 homes | Waiting 3.8 years for a planning decisionWho can move it: Three Rivers Council · planning ref 22/1945/FUL |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| South West Hertfordshire | 0.7 MW | 0 MW | not visible |
| Beaconsfield | 0.4 MW | 0 MW | not visible |
| Ruislip, Northwood and Pinner | 0 MW | 0 MW | not visible |
| Harrow East | 0 MW | 0 MW | not visible |
| Chesham and Amersham | 0 MW | 0 MW | not visible |
| Watford | 0.5 MW | 0.3 MW | not visible |
South West Hertfordshire has more approved-and-waiting capacity than any of its neighbouring seats.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call