CONSTITUENCY BRIEFING · ENERGYMAP.APP

West Aberdeenshire and Kincardine

MP: Andrew Bowie (Conservative) Scotland Data to July 2026

West Aberdeenshire and Kincardine has 211 MW of clean power (almost all onshore wind) approved and still not built: enough to supply a year's electricity to 170,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.8m across the constituency's 41,681 homes. There is also 217 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 19 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Hill of Fare - Hill of Fare Wind Farm & Battery StorageRES Limited Onshore wind 106 MW92,000 homes Waiting 2.7 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004592
Glendye EstateCoriolis Energy/ ESB Onshore wind 104 MW91,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00000676
Hill of Fare - Hill of Fare Wind Farm & Battery StorageRES Limited Battery 100 MW Waiting 2.7 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004592
Bridgend Farm, Arbuthnott - Battery Energy Storage SystemOPDE UK Limted Battery 50 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2025/0089
Old Schoolhouse, Barras - Battery Energy Storage SystemGreen Switch Capital Limited Battery 50 MW Waiting 19 months for a planning decisionWho can move it: Aberdeenshire Council · planning ref APP/2024/2125
Forest Avenue Cottage, Drumlithie - Battery Energy StorageDrumlithie Battery Limited Battery 50 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2023/0940
Meetlaw Farm, Fordoun - Battery Energy Storage SystemOne Planet Developments Limited Battery 50 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2022/2676
Fetteresso Wind Farm (Mid Hill 3)Fred Olsen Renewables Onshore wind 42 MW37,000 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00001851
Craigneil HillESB Asset Development UK Onshore wind 35 MW31,000 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2018/0993
West Bendings - Battery StorageFiddes Battery Limited Battery 30 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2022/2007
Cullerlie Solar FarmElgin Energy ES Co Limited Solar 13 MW4,700 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2021/0378
Coast Viners Animal Nutrition, Drumlithie - Solar Array & Battery StorageEast Coast Viners Renewables Limited Solar 9.2 MW3,300 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2022/1701

Plus 7 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
West Aberdeenshire and Kincardine 211 MW219 MWnot visible
Aberdeen South 4.2 MW0 MWnot visible
Aberdeen North 0.2 MW0.3 MWnot visible
Angus and Perthshire Glens 143 MW345 MW£3.4m
Moray West, Nairn and Strathspey 642 MW525 MW£17m
Gordon and Buchan 107 MW187 MW£120k

Moray West, Nairn and Strathspey next door has 642 MW waiting, more than West Aberdeenshire and Kincardine's 211 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.