CONSTITUENCY BRIEFING · ENERGYMAP.APP

Aberdeen North

MP: Kirsty Blackman (Scottish National Party) Scotland Data to July 2026

Aberdeen North has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.9m across the constituency's 53,821 homes. A 50 MW battery was refused planning here in 2025; while discharging it could have supplied about 175,000 homes.

Ranks 546 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Lower Bodachra - Solar PanelsNovus Renewables Services Limited Solar 72 MW26,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004848
Persley BESS - Battery StorageAnesco Battery 70 MW Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2027 · planning ref ECU00005113
Aryburn Farm, Dyce - Battery StorageSource Galileo Limited Battery 50 MW Refused by Aberdeen City Council in 2025Who can move it: Aberdeen City Council · planning ref 241197/DPP
Persley Croft - Battery StorageRE Projects Development Battery 50 MW Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2026 · planning ref 231134/DPP
Lower Bodachra - Energy Storage SystemNovus Renewables Services Limited Battery 45 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004848
Farburn Place - Battery Energy Storage FacilityPeak Reserve Power Limited / Centrica / Cragside Battery 30 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 210665/DPP

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Aberdeen North 0.2 MW0.3 MWnot visible
Aberdeen South 4.2 MW0 MWnot visible
West Aberdeenshire and Kincardine 211 MW219 MWnot visible
Gordon and Buchan 107 MW187 MW£120k

West Aberdeenshire and Kincardine next door has 211 MW waiting, more than Aberdeen North's 0.2 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.