Gordon and Buchan

MP: Harriet Cross (Conservative) Scotland Data to July 2026

Gordon and Buchan was paid £120k last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 39 hours. A further 107 MW of approved clean power (mostly onshore wind) is still waiting to be built here: enough to supply a year's electricity to 83,000 homes. A 300 MW battery approved at Kintore Battery Energy Storage Project in 2025 would store power that is currently wasted; it has not been built.

Ranks 59 of 650 for clean power approved and not built; 19 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
The Kintore Hydrogen Project, Kintore - Hydrogen PlantStatera Energy Hydrogen 3,000 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2024/1604
Abbotshaugh Battery StorageIsland Green Power (IGP Solar 25 Limited) Battery 500 MW Waiting 15 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005224
Rothienorman, Middleton of Blackhills - BESSBlackford Renewables Limited Battery 500 MW Waiting 13 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006121
Kintore Battery Energy Storage ProjectAlcemi Storage Development Limited Battery 300 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004756
Womblehill Farm, Kintore - Battery Energy Storage SystemRE Projects Development (REPD) / Field Battery 200 MW Waiting 13 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005233
Kinmuck Battery Energy StorageKinmuck Energy Storage Limited / Island Green Power Battery 105 MW Cannot connect to the grid until 2027, 2 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2027 · planning ref ECU00004907
Clashindarroch 2Vattenfall Onshore wind 77 MW67,000 homes Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2027 · planning ref ECU00002002
Clashindarroch Wind Farm ExtensionInfinergy Battery 50 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004695
Kintore - Solar Photovoltaic ArrayMespil Solar Energy Solar 50 MW18,000 homes Waiting 12 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00005245
Kintore Substation, Leylodge - Battery Energy StorageXRE Gamma Limited / EDF Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2023/1234
Fairfield - Battery Energy Storage SystemGreen Switch Capital Battery 50 MW Refused by Aberdeenshire Council in 2026Who can move it: Aberdeenshire Council · planning ref APP/2025/1015
Middleton Of Potterton Farm - Battery Energy Storage SystemGreen Switch Capital (Qair) Battery 50 MW Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO) · earliest connection 2029 · planning ref APP/2025/0313

Plus 20 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Gordon and Buchan 107 MW187 MW£120k
Aberdeen North 0.2 MW0.3 MWnot visible
West Aberdeenshire and Kincardine 211 MW219 MWnot visible
Moray West, Nairn and Strathspey 642 MW525 MW£17m
Aberdeenshire North and Moray East 215 MW122 MWnot visible

Moray West, Nairn and Strathspey next door has 642 MW waiting, more than Gordon and Buchan's 107 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.