Spelthorne has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,805 homes.

Ranks 569 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Sunbury Battery Energy Storage System - Battery Energy Storage SystemEcoDev Group Limited Battery 200 MW Cannot connect to the grid until 2031, 5 years after it was approvedWho can move it: the grid operator (NESO) and National Grid · earliest connection 2031 · planning ref 24/01112/FUL
Long Lane, Stanwell - Battery Energy StorageHarwood Project One Limited Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/01541/FUL
Charlton Lane Eco Park (ACT)SITA UK Advanced Conversion Technologies 3.6 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 10/00947/SCC

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Spelthorne 0 MW0 MWnot visible
Runnymede and Weybridge 0.6 MW1.8 MWnot visible
Esher and Walton 0.3 MW2.4 MWnot visible
Twickenham 0 MW0 MWnot visible
Windsor 0.7 MW4.8 MWnot visible
Feltham and Heston 2.6 MW1.7 MWnot visible

Feltham and Heston next door has 2.6 MW waiting, more than Spelthorne's 0 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.