Runnymede and Weybridge
Runnymede and Weybridge has 2 MW of renewables running, enough for 600 homes over a year, and nothing large waiting in the planning queue. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 43,489 homes.
Ranks 473 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Twynersh Meadows, Thorpe Road - Solar Park & Battery StorageRunnymede Borough Council | Solar | 5.5 MW2,000 homes | Waiting 12 months for a planning decisionWho can move it: Runnymede Council · planning ref RU.25/0843 |
| Twynersh Meadows, Thorpe Road - Solar Park & Battery StorageRunnymede Borough Council | Battery | 5 MW | Waiting 12 months for a planning decisionWho can move it: Runnymede Council · planning ref RU.25/0843 |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Runnymede and Weybridge | 0.6 MW | 1.8 MW | not visible |
| Dorking and Horley | 0.6 MW | 0 MW | not visible |
| Guildford | 1.1 MW | 0 MW | not visible |
| Woking | 1.9 MW | 0 MW | not visible |
| Surrey Heath | 0 MW | 0 MW | not visible |
| Epsom and Ewell | 0.3 MW | 0 MW | not visible |
Woking next door has 1.9 MW waiting, more than Runnymede and Weybridge's 0.6 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call