CONSTITUENCY BRIEFING · ENERGYMAP.APP

Rotherham

MP: Sarah Champion (Labour) England Data to July 2026

Rotherham has 3 MW of renewables running, enough for 2,300 homes over a year, and nothing large waiting in the planning queue. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,916 homes.

Ranks 481 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Whitestone Solar FarmNet Zero One Ltd Solar 750 MW272,000 homes Applied in 2026, still waiting for a decisionWho can move it: the Planning Inspectorate (it decides nationally significant projects) · planning ref EN0110020
Maltby Solar FarmInfinis Energy Services Limited Battery 50 MW Waiting 12 months for a planning decisionWho can move it: Rotherham Council · planning ref 25/01554/FULM
Brinsworth Road, Brinsworth - Battery Energy storageRoot Power South Limited Battery 40 MW Waiting 23 months for a planning decisionWho can move it: Rotherham Council · planning ref RB2024/1307
Claire Court, Rawmarsh Road - Battery Energy Storage FacilityConrad Energy (Developments) Ii Limited Battery 40 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref RB2023/0542
Former Templeborough Steel WorksRolton Kilbride Advanced Conversion Technologies 23 MW Approved 10 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref RB2016/0891
Maltby Solar FarmInfinis Energy Services Limited Solar 20 MW7,300 homes Waiting 12 months for a planning decisionWho can move it: Rotherham Council · planning ref 25/01554/FULM

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Rotherham 0.5 MW2.6 MWnot visible
Rother Valley 49 MW24 MWnot visible
Rawmarsh and Conisbrough 2.2 MW0 MWnot visible
Sheffield South East 6.3 MW0 MWnot visible
Sheffield Brightside and Hillsborough 2.1 MW0 MWnot visible
Penistone and Stocksbridge 0 MW26 MWnot visible

Rother Valley next door has 49 MW waiting, more than Rotherham's 0.5 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.