Penistone and Stocksbridge has 26 MW of renewables running, enough for 23,000 homes over a year, and nothing large waiting in the planning queue. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.6m across the constituency's 39,283 homes. There is also 26 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 569 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Tofts Lane, Hunshelf - Battery StorageHarmony HS (JV) Limited Battery 40 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2023/0322
Yarra Industrial Estate, Loicher Lane - Battery StorageEcclesfield Power Limited Battery 20 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/03914/FUL
Sherwin Williams Diversified Brands, Thorncliffe Road - Solar PanelsSherwin Williams Solar 1.2 MW400 homes Applied in 2026, still waiting for a decisionWho can move it: Sheffield Council · planning ref 26/00980/PVPN
Hazlehead Wind Farm BatteryBanks Renewables Battery 1 MW Approved 6 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2020/0242

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Penistone and Stocksbridge 0 MW26 MWnot visible
High Peak 0.3 MW0 MWnot visible
Rotherham 0.5 MW2.6 MWnot visible
Rawmarsh and Conisbrough 2.2 MW0 MWnot visible
Sheffield Hallam 0 MW0 MWnot visible
Sheffield Brightside and Hillsborough 2.1 MW0 MWnot visible

Rawmarsh and Conisbrough next door has 2.2 MW waiting, more than Penistone and Stocksbridge's 0 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.