Aberdeenshire North and Moray East

MP: Seamus Logan (Scottish National Party) Scotland Data to July 2026

Aberdeenshire North and Moray East has 215 MW of clean power (almost all solar) approved and still not built: enough to supply a year's electricity to 88,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,246 homes. There is also 121 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 18 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Greystone, Blackhills - Battery Energy Storage SystemPeterhead Flexpower Battery 500 MW Waiting 13 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006204
Flushing, Longside - Battery Energy Storage SystemHarmony Energy Storage Battery 400 MW Waiting 13 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006086
Netherton, Langside Road - Battery Energy Storage SystemField Energy Battery 400 MW Applied in 2025, still waiting for a decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006137
Gibson Farm, Blackhillock - Battery Energy Storage SystemNoriker Power Limited Battery 349 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00005237
Blackhillock Electricity Substation - Battery Energy Storage SystemZenobe Energy Limited Battery 300 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00003404
Salamander Offshore Wind Farm - Battery Storage and Onshore ConnectionOrsted / Simply Blue Group Battery 180 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00005201
Aultmore Forest - Buckie - WindfarmVattenfall Onshore wind 106 MW92,000 homes Waiting 2.4 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00003365
Frodo Solar and Battery Energy DevelopmentGreen Energy International Solar 60 MW22,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003345
Greenbank Caravan & Trailers, Hillhead Of Phingask - Battery StorageFlexion Energy UK Storage Battery 50 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2022/1988
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage FacilityElgin Energy Es Co Limited Solar 50 MW18,000 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003226
Frodo Solar and Battery Energy DevelopmentGreen Energy International Battery 50 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003345
Electricity Sub Station, Strichen - Battery Storage FacilityIntelligent Land Investments Group plc Battery 50 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref APP/2021/2556

Plus 26 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Aberdeenshire North and Moray East 215 MW122 MWnot visible
Moray West, Nairn and Strathspey 642 MW525 MW£17m
Gordon and Buchan 107 MW187 MW£120k

Moray West, Nairn and Strathspey next door has 642 MW waiting, more than Aberdeenshire North and Moray East's 215 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.