CONSTITUENCY BRIEFING · ENERGYMAP.APP

Oldham West, Chadderton and Royton

MP: Jim McMahon (Labour (Co-op)) England Data to July 2026

Oldham West, Chadderton and Royton has 2.8 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,416 homes.

Ranks 306 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Whitegate Battery StoragePelagic Energy (Constantine Energy) Battery 57 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref FUL/348501/22
Chadderton - Battery energy storage facilityField Battery 20 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref FUL/348758/22
IGC, Lydia Becker Way - Solar PanelsAshcroft Electrical Services Limited Solar 3.1 MW1,100 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref SONDPR/354801/25
Chadderton - Battery Storage SystemZetex Plc Battery 2.5 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref FUL/348617/22

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Oldham West, Chadderton and Royton 2.8 MW0 MWnot visible
Ashton-under-Lyne 0.9 MW0 MWnot visible
Manchester Central 2.9 MW4.1 MWnot visible
Blackley and Middleton South 0.3 MW0.1 MWnot visible
Oldham East and Saddleworth 0.5 MW0 MWnot visible
Heywood and Middleton North 5.9 MW0 MWnot visible

Heywood and Middleton North next door has 5.9 MW waiting, more than Oldham West, Chadderton and Royton's 2.8 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.