CONSTITUENCY BRIEFING · ENERGYMAP.APP
Ashton-under-Lyne
Ashton-under-Lyne has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,224 homes.
Ranks 429 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Holden WaySTOR Power | Battery | 6 MW | Approved 8 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 17/00846/FUL |
| Tameside General Hospital - Energy CentreTameside & Glossop Acute Services NHS Trust | Air Source Heat Pumps | 2 MW | Applied in 2026, still waiting for a decisionWho can move it: Tameside Council · planning ref 26/00405/FUL |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Ashton-under-Lyne | 0.9 MW | 0 MW | not visible |
| Gorton and Denton | 0.5 MW | 1.9 MW | not visible |
| Stalybridge and Hyde | 0.2 MW | 3 MW | not visible |
| Manchester Central | 2.9 MW | 4.1 MW | not visible |
| Oldham West, Chadderton and Royton | 2.8 MW | 0 MW | not visible |
| Oldham East and Saddleworth | 0.5 MW | 0 MW | not visible |
Manchester Central next door has 2.9 MW waiting, more than Ashton-under-Lyne's 0.9 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting