North East Cambridgeshire

MP: Steve Barclay (Conservative) England Data to July 2026

North East Cambridgeshire has 2.9 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,100 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,083 homes. There is also 133 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 300 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Medworth EfWMVV Environment EfW Incineration 58 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref EN010110
Treading Bank Solar FarmRenewable Connections Solar 50 MW18,000 homes Refused by Fenland Council in 2025Who can move it: Fenland Council · planning ref F/YR25/0758/F
West Fen Farm, Whitemoor Road - Solar FarmPathfinder Clean Energy UK Dev Limited Solar 50 MW18,000 homes Waiting 14 months for a planning decisionWho can move it: Fenland Council · planning ref F/YR25/0413/F
West Fen Farm, Whitemoor Road - Battery StoragePathfinder Clean Energy UK Dev Limited Battery 30 MW Waiting 14 months for a planning decisionWho can move it: Fenland Council · planning ref F/YR25/0413/F
Tydd Solar FarmPathfinder Clean Energy UK Dev Limited Solar 25 MW9,100 homes Refused by Powys Council in 2025Who can move it: Powys Council · planning ref H19-0329-24
Tydd Solar FarmPathfinder Clean Energy UK Dev Limited Solar 25 MW9,100 homes Refused by Fenland Council in 2025Who can move it: Fenland Council · planning ref F/YR24/0457/F
Tydd Solar FarmPathfinder Clean Energy UK Dev Limited Battery 15 MW Refused by Powys Council in 2025Who can move it: Powys Council · planning ref H19-0329-24
Tydd Solar FarmPathfinder Clean Energy UK Dev Limited Battery 15 MW Refused by Fenland Council in 2025Who can move it: Fenland Council · planning ref F/YR24/0457/F
Kings Dyke, Whittlesey - Battery Energy StoragePower Initiatives Limited Battery 10 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref F/YR24/0932/F

Plus 2 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
North East Cambridgeshire 2.9 MW156 MWnot visible
Huntingdon 32 MW157 MWnot visible
North West Cambridgeshire 13 MW20 MWnot visible
Peterborough 67 MW30 MWnot visible
South Holland and The Deepings 130 MW113 MWnot visible
Ely and East Cambridgeshire 145 MW257 MWnot visible

Ely and East Cambridgeshire next door has 145 MW waiting, more than North East Cambridgeshire's 2.9 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.