CONSTITUENCY BRIEFING · ENERGYMAP.APP
Mid Dunbartonshire
Mid Dunbartonshire has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 40,272 homes.
Ranks 569 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Whitehall Battery StorageApatura | Battery | 560 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004982 |
| Windyhill Battery Storage FacilityEnergy GridPower Ltd / Revera Energy | Battery | 200 MW | Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2027 · planning ref ECU00003361 |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Mid Dunbartonshire | 0 MW | 0.8 MW | not visible |
| Glasgow North East | 0.1 MW | 0 MW | not visible |
| Glasgow North | 19 MW | 0 MW | not visible |
| Glasgow West | 0.5 MW | 0 MW | not visible |
| Cumbernauld and Kirkintilloch | 1.2 MW | 0 MW | not visible |
| West Dunbartonshire | 0.5 MW | 0 MW | not visible |
Glasgow North next door has 19 MW waiting, more than Mid Dunbartonshire's 0 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call
Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.