CONSTITUENCY BRIEFING · ENERGYMAP.APP
Glasgow North East
Glasgow North East has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.6m across the constituency's 50,217 homes.
Ranks 567 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Whitehill Energy StorageIntelligent Land Investments Group | Battery | 200 MW | Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2028 · planning ref ECU00004632 |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Glasgow North East | 0.1 MW | 0 MW | not visible |
| Glasgow East | 0.5 MW | 0 MW | not visible |
| Coatbridge and Bellshill | 0.6 MW | 0.2 MW | not visible |
| Glasgow North | 19 MW | 0 MW | not visible |
| Cumbernauld and Kirkintilloch | 1.2 MW | 0 MW | not visible |
| Mid Dunbartonshire | 0 MW | 0.8 MW | not visible |
Glasgow North next door has 19 MW waiting, more than Glasgow North East's 0.1 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call