Glasgow North
Glasgow North has 19 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 7,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.6m across the constituency's 49,545 homes.
Ranks 200 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Caledonian Solar ParkDerwent London Green Energy Limited | Solar | 18 MW6,700 homes | Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 21/03239/FUL |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Glasgow North | 19 MW | 0 MW | not visible |
| Glasgow East | 0.5 MW | 0 MW | not visible |
| Glasgow North East | 0.1 MW | 0 MW | not visible |
| Glasgow West | 0.5 MW | 0 MW | not visible |
| Mid Dunbartonshire | 0 MW | 0.8 MW | not visible |
Glasgow North has more approved-and-waiting capacity than any of its neighbouring seats.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call
Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.