Midlothian

MP: Kirsty McNeill (Labour (Co-op)) Scotland Data to July 2026

Midlothian has 4.2 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,500 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,009 homes.

Ranks 275 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Salters Battery Energy Storage SystemBuccleuch Group Battery 200 MW Cannot connect to the grid until 2031, 6 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2031 · planning ref ECU00004962
Penicuik, Moorfoot Hills - Torfichen Wind FarmRES Limited Onshore wind 108 MW94,000 homes Waiting 2.7 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004661
Penicuik, Moorfoot Hills - Torfichen Wind FarmRES Limited Battery 50 MW Waiting 2.7 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004661
Easter BushUniversity of Edinburgh (Estates Department) Solar 3 MW1,100 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 19/00022/DPP

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Midlothian 4.2 MW0 MWnot visible
Dumfriesshire, Clydesdale and Tweeddale 913 MW1,451 MW£15m
Edinburgh South West 0 MW0 MWnot visible
Edinburgh South 0 MW0 MWnot visible
Berwickshire, Roxburgh and Selkirk 85 MW685 MW£7.0m
Lothian East 0.4 MW216 MW£3.2m

Dumfriesshire, Clydesdale and Tweeddale next door has 913 MW waiting, more than Midlothian's 4.2 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call