CONSTITUENCY BRIEFING · ENERGYMAP.APP
Bury South
Bury South has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,756 homes.
Ranks 512 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Shore Top Farm, Kearsley Road - Battery Energy StorageTaiyo Power & Storage Limited | Battery | 11 MW | Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 71888 |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Bury South | 0.4 MW | 0 MW | not visible |
| Manchester Central | 2.9 MW | 4.1 MW | not visible |
| Blackley and Middleton South | 0.3 MW | 0.1 MW | not visible |
| Heywood and Middleton North | 5.9 MW | 0 MW | not visible |
| Salford | 0.6 MW | 0 MW | not visible |
| Bolton South and Walkden | 3.6 MW | 5 MW | not visible |
Heywood and Middleton North next door has 5.9 MW waiting, more than Bury South's 0.4 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call