Brecon, Radnor and Cwm Tawe
Brecon, Radnor and Cwm Tawe has 39 MW of clean power (mostly solar) approved and still not built: enough to supply a year's electricity to 22,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.8m across the constituency's 41,649 homes. There is also 83 MW of wind running here on the local network. If that gets switched off, no national record shows it.
Ranks 160 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Radnor Forest, Llandegley - Nant Mithil Energy ParkBute Energy | Onshore wind | 198 MW173,000 homes | Applied in 2025, still waiting for a decisionWho can move it: the Welsh Government (it decides big energy projects) · planning ref DNS - CAS-01907-D7Q6Z1 |
| Garn Fach Wind FarmEDF Renewables | Onshore wind | 85 MW74,000 homes | Cannot connect to the grid until 2037, 13 years after it was approvedWho can move it: the grid operator (NESO) and National Grid · earliest connection 2037 · planning ref DNS/3244499 |
| Garn Fach Wind FarmEDF Renewables | Battery | 50 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DNS/3244499 |
| Bryngydfa Wind FarmPrivate Developer | Onshore wind | 36 MW31,000 homes | Waiting 17.3 years for a planning decisionWho can move it: Powys Council · planning ref P/2009/0384 |
| Bryn HenllysLightsource BP | Solar | 20 MW7,300 homes | Approved 8 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P/2015/0176 |
| Hendy Wind FarmNjord Energy Ltd | Onshore wind | 14 MW13,000 homes | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref P/2014/0672 |
Plus 3 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Brecon, Radnor and Cwm Tawe | 39 MW | 87 MW | not visible |
| Gower | 0 MW | 62 MW | not visible |
| Neath and Swansea East | 27 MW | 58 MW | not visible |
| North Herefordshire | 2.3 MW | 50 MW | not visible |
| Merthyr Tydfil and Aberdare | 10 MW | 31 MW | not visible |
| Blaenau Gwent and Rhymney | 66 MW | 23 MW | not visible |
Blaenau Gwent and Rhymney next door has 66 MW waiting, more than Brecon, Radnor and Cwm Tawe's 39 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call