CONSTITUENCY BRIEFING · ENERGYMAP.APP

Blaenau Gwent and Rhymney

MP: Nick Smith (Labour) Wales Data to July 2026

Blaenau Gwent and Rhymney has 66 MW of clean power (onshore wind and solar) approved and still not built: enough to supply a year's electricity to 42,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.9m across the constituency's 42,525 homes.

Ranks 101 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Mynydd Carn Wind FarmPennant Walters Onshore wind 34 MW30,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DNS/3270299
Wauntysswg Farm, near TredagarElgin Energy Solar 30 MW11,000 homes Approved 7 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DNS/3213639
Pen March Wind FarmRWE Renewables UK Limited Onshore wind 30 MW26,000 homes Refused by the Welsh Government (it decides big energy projects) in 2025Who can move it: the Welsh Government (it decides big energy projects) · planning ref DNS/3253147
Manmoel Wind FarmCenin Renewables Onshore wind 28 MW24,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DNS/3239181
Convatec Green Manufacturing HubConvatec Limited Onshore wind 15 MW13,000 homes Refused by the Welsh Government (it decides big energy projects) in 2025Who can move it: the Welsh Government (it decides big energy projects) · planning ref CAS-02977-Y9F1W7
Rassau Industrial Estate, Rassau - Battery Energy StoragePrivate Developer Battery 8 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref C/2023/0078
Rassau Industrial EstatePrivate Developer Battery 6 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref C/2019/0326
Convatec Green Manufacturing HubConvatec Limited Solar 5 MW1,800 homes Refused by the Welsh Government (it decides big energy projects) in 2025Who can move it: the Welsh Government (it decides big energy projects) · planning ref CAS-02977-Y9F1W7

Plus 2 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Blaenau Gwent and Rhymney 66 MW23 MWnot visible
Caerphilly 20 MW32 MWnot visible
Newport West and Islwyn 0.3 MW22 MWnot visible
Torfaen 3.5 MW10 MWnot visible
Merthyr Tydfil and Aberdare 10 MW31 MWnot visible
Monmouthshire 33 MW39 MWnot visible

Blaenau Gwent and Rhymney has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.