Merthyr Tydfil and Aberdare

MP: Gerald Jones (Labour) Wales Data to July 2026

Merthyr Tydfil and Aberdare has 10 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 3,700 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,830 homes. There is also 22 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 227 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Cefn Farm, Mount Road - Battery Energy Storage SystemTec Marina Battery 200 MW Waiting 15 months for a planning decisionWho can move it: Rhondda Cynon Taf Council · planning ref 25/0536/FUL
Rhigos Road - Solar FarmRegener8 Power / Environmena Solar 9.9 MW3,600 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 23/0820/10
Pengarnddu Industrial Estate, Dowlais - Hydrogen Electrolyser Plant FacilityConrad Energy (Developments) Limited Hydrogen 8 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P/24/0196
Pen Y Dre High School, Goitre Lane - Solar PanelsMerthyr Tydfil County Borough Council Solar 1.4 MW500 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P/25/0044

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Merthyr Tydfil and Aberdare 10 MW31 MWnot visible
Aberafan Maesteg 37 MW313 MW£470k
Neath and Swansea East 27 MW58 MWnot visible
Pontypridd 41 MW42 MWnot visible
Caerphilly 20 MW32 MWnot visible
Rhondda and Ogmore 81 MW114 MWnot visible

Rhondda and Ogmore next door has 81 MW waiting, more than Merthyr Tydfil and Aberdare's 10 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.