CONSTITUENCY BRIEFING · ENERGYMAP.APP
Wyre Forest
Wyre Forest has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.2m across the constituency's 45,320 homes.
Ranks 429 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Kidderminster Energy and Resource ParkPower Generation Solutions | EfW Incineration | 5 MW | Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 20/000034/CM |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Wyre Forest | 0.9 MW | 0 MW | not visible |
| Droitwich and Evesham | 67 MW | 122 MW | not visible |
| Redditch | 3.3 MW | 5.2 MW | not visible |
| Bromsgrove | 51 MW | 0.7 MW | not visible |
| West Worcestershire | 5.8 MW | 95 MW | not visible |
| South Shropshire | 112 MW | 78 MW | not visible |
South Shropshire next door has 112 MW waiting, more than Wyre Forest's 0.9 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 1 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call
Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.