CONSTITUENCY BRIEFING · ENERGYMAP.APP

Droitwich and Evesham

MP: Nigel Huddleston (Conservative) England Data to July 2026

Droitwich and Evesham has 67 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 24,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,897 homes.

Ranks 100 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Fibden Farm - Solar ArrayGrenergy Renewables Solar 40 MW15,000 homes Waiting 2.1 years for a planning decisionWho can move it: Wychavon Council · planning ref W/24/01088/FUL
Fibden Farm, Hampton Lovett - Solar ArrayGrenergy Renewables Solar 40 MW15,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref W/24/01088/FUL
Mount Farm, Mount Pleasant - Solar FarmMount Farm Solar Limited Solar 35 MW13,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/01085/FUL
Bishampton Solar FarmInfinis Solar 30 MW11,000 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 20/02071/FUL
Crossway Green, Ombersley - Solar PanelsTyler Hill Solar Limited Solar 18 MW6,500 homes Waiting 2.8 years for a planning decisionWho can move it: Wychavon Council · planning ref W/23/01894/FUL
Pershore Lane, Tibberton - Battery Energy Storage SystemSirius Renewable Energy Battery 14 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref W/22/02717/FUL
Norchard FarmNorchard Solar Farm Limited Solar 8.8 MW3,200 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref W/23/01483/FUL

Plus 5 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Droitwich and Evesham 67 MW122 MWnot visible
Stratford-on-Avon 134 MW39 MWnot visible
North Cotswolds 55 MW14 MWnot visible
Tewkesbury 66 MW41 MWnot visible
Redditch 3.3 MW5.2 MWnot visible
West Worcestershire 5.8 MW95 MWnot visible

Stratford-on-Avon next door has 134 MW waiting, more than Droitwich and Evesham's 67 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.