CONSTITUENCY BRIEFING · ENERGYMAP.APP

Bromsgrove

MP: Bradley Thomas (Conservative) England Data to July 2026

Bromsgrove has 51 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 18,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,266 homes.

Ranks 130 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Illey Lane - Battery Energy StorageGrenergy Renewables UK Limited Battery 70 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00960/FUL
Foxwalks Farm, Grafton Lane - Solar FarmSpring Dev 10 Limited Solar 50 MW18,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00896/FUL
Foxwalks Solar Farm - ExtensionSpring Dev 10 Limited Solar 13 MW4,700 homes Applied in 2026, still waiting for a decisionWho can move it: Bromsgrove Council · planning ref 26/00187/FUL

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Bromsgrove 51 MW0.7 MWnot visible
Stratford-on-Avon 134 MW39 MWnot visible
Redditch 3.3 MW5.2 MWnot visible
Solihull West and Shirley 1.8 MW0 MWnot visible
Birmingham Northfield 0.9 MW0 MWnot visible
Birmingham Selly Oak 0 MW0 MWnot visible

Stratford-on-Avon next door has 134 MW waiting, more than Bromsgrove's 51 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.