Worsley and Eccles

MP: Michael Wheeler (Labour) England Data to July 2026

Worsley and Eccles has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.2m across the constituency's 46,032 homes.

Ranks 500 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Whitehead Landfill Site, Lower Green Lane - Solar FarmWhitehead Restoration Limited Solar 10 MW3,600 homes Waiting 23 months for a planning decisionWho can move it: Wigan Council · planning ref PA/2024/0759

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Worsley and Eccles 0.4 MW0 MWnot visible
Warrington North 11 MW0 MWnot visible
Stretford and Urmston 1.8 MW0 MWnot visible
Leigh and Atherton 0 MW0.5 MWnot visible
Salford 0.6 MW0 MWnot visible
Bolton South and Walkden 3.6 MW5 MWnot visible

Warrington North next door has 11 MW waiting, more than Worsley and Eccles's 0.4 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call