MP: Charlie Maynard (Liberal Democrat) England Data to July 2026

Witney has 48 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 17,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.7m across the constituency's 40,272 homes.

Ranks 146 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Witney Bypass, Stanton Harcourt Road - Battery StorageVoltwise Power Holdings Limited Battery 150 MW Waiting 12 months for a planning decisionWho can move it: West Oxfordshire Council · planning ref 25/01656/FUL
Willowfields Energy Park, Marcham - Solar PanelsExagen Development Limited Solar 50 MW18,000 homes Waiting 19 months for a planning decisionWho can move it: Vale of White Horse Council · planning ref P24/V2698/FUL
Aston Road, Aston - Solar Panels & Battery Energy Storage SystemAmpyr Solar Europe Solar 40 MW15,000 homes Waiting 12 months for a planning decisionWho can move it: West Oxfordshire Council · planning ref 25/01702/FUL
Aston Road, Aston - Solar Panels & Battery Energy Storage SystemAmpyr Solar Europe Battery 40 MW Waiting 12 months for a planning decisionWho can move it: West Oxfordshire Council · planning ref 25/01702/FUL
Snowswick Lane, Coleshill - Solar FarmAbei Energy Limited Solar 40 MW14,000 homes Applied in 2025, still waiting for a decisionWho can move it: Vale of White Horse Council · planning ref P25/V1646/FUL
Ducklington Solar FarmNovus Renewable Services / Innova Renewables Solar 36 MW13,000 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 21/01236/FUL
Quarry Solar Farm & Battery Storage FacilityRWE Solar 35 MW13,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/01565/FUL
Quarry Solar Farm & Battery Storage FacilityJBM Solar Projects 34 Limited Battery 35 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/01565/FUL
Snowswick Lane, Coleshill - Solar FarmAbei Energy Limited Battery 25 MW Applied in 2025, still waiting for a decisionWho can move it: Vale of White Horse Council · planning ref P25/V1646/FUL
Akeman Solar Park & Battery StorageBritish Solar Renewables Solar 20 MW7,300 homes Refused by West Oxfordshire Council in 2025Who can move it: West Oxfordshire Council · planning ref 25/00234/FUL
Willowfields Energy Park, Marcham - Battery Energy StorageExagen Development Limited Battery 20 MW Waiting 19 months for a planning decisionWho can move it: Vale of White Horse Council · planning ref P24/V2698/FUL
Shilton Road - Solar ParkEcotricity Generation Limited Solar 8 MW2,900 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/02472/FUL

Plus 3 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Witney 48 MW61 MWnot visible
Newbury 5.4 MW18 MWnot visible
East Wiltshire 2.3 MW63 MWnot visible
Swindon North 58 MW105 MWnot visible
Banbury 10 MW20 MWnot visible
Didcot and Wantage 103 MW121 MWnot visible

Didcot and Wantage next door has 103 MW waiting, more than Witney's 48 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.