CONSTITUENCY BRIEFING · ENERGYMAP.APP
Didcot and Wantage
Didcot and Wantage has 103 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 37,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.1m across the constituency's 44,055 homes.
Ranks 65 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Culham Science Centre, Clifton Hampden - Battery Storage FacilityStatera Energy | Battery | 500 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P24/S1498/FUL |
| Appleford - Battery Energy StorageTBC 001 Limited | Battery | 300 MW | Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P25/V0149/FUL |
| Cowley Substation, Blackberry Lane - Battery Storage Energy SystemPenso Power (BW ESS) | Battery | 200 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P24/S3405/FUL |
| Burcot Solar FarmEthical Power | Battery | 50 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P23/S4132/FUL |
| Barnstaples FarmNextpower SPV 14 Limited | Solar | 50 MW18,000 homes | Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P21/V3395/FUL |
| Nuneham Courtenay Solar Farm & Battery Storage FacilityEnso Energy (Cowley Baldon Green Limited) | Solar | 50 MW18,000 homes | Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P20/S4360/FUL |
| Nuneham Courtenay - Solar FarmRES Limited | Solar | 50 MW18,000 homes | Waiting 2.3 years for a planning decisionWho can move it: South Oxfordshire Council · planning ref P24/S1336/FUL |
| Burcot Solar FarmEthical Power | Solar | 50 MW18,000 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P23/S4132/FUL |
| Manor Farm, Denchworth - Solar Photovoltaic PanelsRenewable Connections Limited | Solar | 30 MW11,000 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P23/V2673/FUL |
| Appleford Sidings, Sutton Courtenay - Solar Photovoltaic ArrayInfinis Solar Developments Limited | Solar | 24 MW8,700 homes | Waiting 5.2 years for a planning decisionWho can move it: Vale of White Horse Council · planning ref MW.0069/21 |
Plus 1 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Didcot and Wantage | 103 MW | 121 MW | not visible |
| Newbury | 5.4 MW | 18 MW | not visible |
| Reading West and Mid Berkshire | 32 MW | 22 MW | not visible |
| Witney | 48 MW | 61 MW | not visible |
| Henley and Thame | 151 MW | 35 MW | not visible |
| Oxford West and Abingdon | 2.7 MW | 0 MW | not visible |
Henley and Thame next door has 151 MW waiting, more than Didcot and Wantage's 103 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call