CONSTITUENCY BRIEFING · ENERGYMAP.APP
Winchester
Winchester has 19 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 6,900 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,375 homes.
Ranks 202 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Silkstead Farm, Poles Lane - Battery Energy Storage SystemWinchester Energy Reserve Limited | Battery | 50 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/01007/FUL |
| South Lynch Farm - Solar FarmNovus Renewable Services Limited | Solar | 20 MW7,300 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/01025/FUL |
| New Farm House Locks FarmNextpower Spv 12 Limited | Solar | 18 MW6,500 homes | Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 21/01391/FUL |
| Stockbridge RoadWinchester Power | Battery | 10 MW | Approved 9 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 17/02575/FUL |
| Glebe Farm, Curdridge Lane - Solar FarmGlebe Farm Energy Limited | Solar | 10 MW3,600 homes | Waiting 14 months for a planning decisionWho can move it: Winchester Council · planning ref 25/01050/FUL |
| Western Court, Bishops Sutton Road - Solar FarmILOS Energy UK Limited | Solar | 5.4 MW2,000 homes | Applied in 2026, still waiting for a decisionWho can move it: Winchester Council · planning ref 26/00707/FUL |
| Home Farm, Hursley Park Road - Solar PanelsClean Energy Capital (CEC) Limited | Solar | 5 MW1,800 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 25/00360/FUL |
Plus 1 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Winchester | 19 MW | 58 MW | not visible |
| Hamble Valley | 6.5 MW | 18 MW | not visible |
| Fareham and Waterlooville | 11 MW | 48 MW | not visible |
| Eastleigh | 29 MW | 6.3 MW | not visible |
| East Hampshire | 78 MW | 56 MW | not visible |
| Basingstoke | 2.1 MW | 0 MW | not visible |
East Hampshire next door has 78 MW waiting, more than Winchester's 19 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures