Fareham and Waterlooville
Fareham and Waterlooville has 11 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 3,900 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,844 homes.
Ranks 224 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Titchfield Lane, Wickham - Solar PanelsConrad Energy (Developments) II Limited | Solar | 50 MW18,000 homes | Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/02804/FUL |
| Titchfield LaneBalanced Grid Solutions | Battery | 49 MW | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 19/02710/FUL |
| Ash Farm, Titchfield Lane - Battery StorageBotley Energy Reserve 2 Limited | Battery | 15 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/01106/FUL |
| Funtley Solar Photovoltaic PV FarmPrivate Developer | Solar | 10 MW3,800 homes | Waiting 23 months for a planning decisionWho can move it: Winchester Council · planning ref HCC/2024/0503 |
| Fontley House FarmJardin Smith International | Solar | 10 MW3,600 homes | Approved 9 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 16/00863/FUL |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Fareham and Waterlooville | 11 MW | 48 MW | not visible |
| Gosport | 1.1 MW | 20 MW | not visible |
| Portsmouth North | 12 MW | 1.2 MW | not visible |
| Havant | 1.5 MW | 0 MW | not visible |
| Hamble Valley | 6.5 MW | 18 MW | not visible |
| Winchester | 19 MW | 58 MW | not visible |
Winchester next door has 19 MW waiting, more than Fareham and Waterlooville's 11 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call
Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.