Tewkesbury
Tewkesbury has 66 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 24,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,561 homes.
Ranks 102 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Claydon Farm - Solar Farm & Battery StorageJBM Solar Projects 17 Limited | Solar | 50 MW18,000 homes | Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 21/00259/FUL |
| Claydon Farm - Solar Farm & Battery StorageJBM Solar Projects 17 Limited | Battery | 50 MW | Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 21/00259/FUL |
| Bengrove Farm, Base Lane - Battery StorageBengrove Bess Limited | Battery | 50 MW | Waiting 3.7 years for a planning decisionWho can move it: Tewkesbury Council · planning ref 22/01231/FUL |
| Tredington House Farm, Tredington - Battery Energy Storage FacilityGreenfield Energy Developments Ltd | Battery | 40 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00411/FUL |
| Home FarmCanadian Solar / Novergy | Solar | 25 MW9,100 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref W/23/01011/FUL |
| Cox's Brook Solar Farm - Solar ArrayPS Renewables Limited | Solar | 16 MW5,800 homes | Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00441/FUL |
| Bengrove Farm, Base Lane - Solar FarmSonnedix Bengrove Limited | Solar | 15 MW5,400 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00050/FUL |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Tewkesbury | 66 MW | 41 MW | not visible |
| Cheltenham | 0.5 MW | 0 MW | not visible |
| North Cotswolds | 55 MW | 14 MW | not visible |
| Droitwich and Evesham | 67 MW | 122 MW | not visible |
| Forest of Dean | 64 MW | 98 MW | not visible |
| Gloucester | 7.2 MW | 0 MW | not visible |
Droitwich and Evesham next door has 67 MW waiting, more than Tewkesbury's 66 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call