CONSTITUENCY BRIEFING · ENERGYMAP.APP

North Ayrshire and Arran

MP: Irene Campbell (Labour) Scotland Data to July 2026

North Ayrshire and Arran has 74 MW of clean power (mostly solar) approved and still not built: enough to supply a year's electricity to 33,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,516 homes. There is also 100 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 92 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Hunterston Grid Services Complex - Energy Storage FacilityAmp Energy Battery 400 MW Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003319
Flemyland Battery StorageFlemyland Battery Storage Limited Battery 100 MW Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2029 · planning ref ECU00004984
High Boydstone Farm - Battery Energy Storage FacilityNew Energy Partnership Battery 100 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00005094
Crosbie Wind FarmGalileo Green Energy Scotland Limited (GGE Scotland) Onshore wind 98 MW86,000 homes Waiting 18 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004981
Benthead Farm - Solar Farm & Battery StorageLocogen Limited Solar 63 MW23,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004702
Crosbie Wind FarmGalileo Green Energy Scotland Limited (GGE Scotland) Battery 50 MW Waiting 18 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004981
Benthead Farm - Solar Farm & Battery StorageLocogen Limited Battery 31 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004702
Meiklelaught Farm - Battery StorageGreen Power Consultants Battery 30 MW Cannot connect to the grid until 2028, 5 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2028 · planning ref 23/00731/PPM
Swinlees Wind FarmThe Farm Energy Partnership Onshore wind 26 MW22,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00843/PPM
Ardoch FarmCapbal Battery 20 MW Cannot connect to the grid until 2026, 1 year after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2026 · planning ref 24/00941/PPM
Wardlaw Wood Windfarm - Battery StorageCommunity Windpower Limited Battery 20 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00593/PP
Wardlaw Wood - Solar FarmCommunity Windpower Limited Solar 20 MW7,300 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00773/PP

Plus 6 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
North Ayrshire and Arran 74 MW105 MWnot visible
Central Ayrshire 51 MW10 MWnot visible
Kilmarnock and Loudoun 82 MW283 MW£900k
East Renfrewshire 0.5 MW361 MW£4.6m
Paisley and Renfrewshire South 0 MW0 MWnot visible
Inverclyde and Renfrewshire West 1.3 MW24 MWnot visible

Kilmarnock and Loudoun next door has 82 MW waiting, more than North Ayrshire and Arran's 74 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.