CONSTITUENCY BRIEFING · ENERGYMAP.APP

Central Ayrshire

MP: Alan Gemmell (Labour) Scotland Data to July 2026

Central Ayrshire has 51 MW of clean power (almost all solar) approved and still not built: enough to supply a year's electricity to 20,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.8m across the constituency's 41,117 homes.

Ranks 129 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Camsiscan Farm, Craigie - Battery Energy Storage SystemNoriker Power Limited Battery 350 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004658
Belston Battery StorageKX Alpha Ltd Battery 150 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00005141
Kilwinning Battery StorageApatura Battery 100 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00005128
Holmston Road - Battery Storage FacilityField Energy Battery 50 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 22/00505/PAN
Glaxosmithkline Shewalton RoadGlaxosmithkline Solar 20 MW7,200 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 19/00163/PP
Wee Minnemoer, Millport - Solar Farm & Battery StorageComsol Energy Solar 19 MW6,900 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00114/PP
Oldhall Industrial EstateDover Yard EfW Incineration 17 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 19/00539/PPM
Olympic Business Park, Dundonald - 2 Wind TurbinesThe Farm Energy Partnership Onshore wind 8.5 MW7,500 homes Refused by South Ayrshire Council in 2024Who can move it: South Ayrshire Council · planning ref 24/00063/APP
Nethermains - Solar FarmNorth Ayrshire Council Solar 7.5 MW2,700 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 23/00317/PP
Dunlop Place, Meadowhead Industrial Estate - Wind turbineFarm Energy Company Onshore wind 7 MW6,100 homes Waiting 12 months for a planning decisionWho can move it: North Ayrshire Council · planning ref 25/00334/PP
Shewalton Landfill Solar FarmNorth Ayrshire Council Solar 5 MW1,800 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 23/00318/PP

Plus 4 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Central Ayrshire 51 MW10 MWnot visible
Ayr, Carrick and Cumnock 654 MW874 MW£18m
Kilmarnock and Loudoun 82 MW283 MW£900k
North Ayrshire and Arran 74 MW105 MWnot visible

Ayr, Carrick and Cumnock next door has 654 MW waiting, more than Central Ayrshire's 51 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.