Paisley and Renfrewshire South
Paisley and Renfrewshire South has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.2m across the constituency's 45,518 homes.
Ranks 569 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Neilston Greener Grid Park - Phase 2Statkraft UK LTD | Battery | 750 MW | Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2029 · planning ref ECU00004988 |
| Neilston - Battery StorageApatura (GPC 1119 Ltd) | Battery | 150 MW | Its grid connection date of 2025 has passed and it is still not generatingWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2025 · planning ref ECU00004868 |
| Neilston Greener Grid ParkStatkraft UK LTD | Battery | 50 MW | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 21/0034/PP |
| Well Street - Battery StorageLarkfleet Group | Battery | 50 MW | Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2028 · planning ref 23/0018/PP |
| Middleton Farm Cottage, Middleton Road - Solar Photovoltaic ArrayBluestone Energy Limited | Solar | 40 MW15,000 homes | Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 25/0232/PP |
Plus 1 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Paisley and Renfrewshire South | 0 MW | 0 MW | not visible |
| North Ayrshire and Arran | 74 MW | 105 MW | not visible |
| East Renfrewshire | 0.5 MW | 361 MW | £4.6m |
| Glasgow South West | 1.1 MW | 0.2 MW | not visible |
| Paisley and Renfrewshire North | 102 MW | 0 MW | not visible |
| Inverclyde and Renfrewshire West | 1.3 MW | 24 MW | not visible |
Paisley and Renfrewshire North next door has 102 MW waiting, more than Paisley and Renfrewshire South's 0 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call