CONSTITUENCY BRIEFING · ENERGYMAP.APP

Pontypridd

MP: Alex Davies-Jones (Labour) Wales Data to July 2026

Pontypridd has 41 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 15,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,273 homes. There is also 23 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 158 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Pound Farm Lane - Battery StoragePulse Clean Energy Battery 200 MW Applied in 2025, still waiting for a decisionWho can move it: Rhondda Cynon Taf Council · planning ref 25/1231/FUL
National Road, Cilfynydd - Battery Energy Storage SystemRewe 2 Limited Battery 200 MW Waiting 14 months for a planning decisionWho can move it: Rhondda Cynon Taf Council · planning ref 25/0604/FUL
Glyntaff Solar Farm, Bryntail Road - Solar ArrayRenantis Falck Renewables Limited Solar 40 MW14,000 homes Waiting 15 months for a planning decisionWho can move it: the Welsh Government (it decides big energy projects) · planning ref CAS-03147-D7S9P8
Llanwonno - Wind FarmCenin Renewables Limited Solar 31 MW11,000 homes Waiting 17 months for a planning decisionWho can move it: the Welsh Government (it decides big energy projects) · planning ref CAS-02125-Q0T5P0
Llanwonno - Wind FarmCenin Renewables Limited Onshore wind 30 MW27,000 homes Waiting 17 months for a planning decisionWho can move it: the Welsh Government (it decides big energy projects) · planning ref CAS-02125-Q0T5P0
Maes Mawr SolarElgin Energy EsCo Ltd Solar 30 MW11,000 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref DNS/3282038
Llanwonno - Wind FarmCenin Renewables Limited Battery 30 MW Waiting 17 months for a planning decisionWho can move it: the Welsh Government (it decides big energy projects) · planning ref CAS-02125-Q0T5P0
Talbot Green, Llantrisant - Solar FarmWindel Energy Solar 9.9 MW3,600 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/1413/10
Dyffryn Farm, Ynysmaerdy - Solar PanelsWindel Solar 8 Limited Solar 9.9 MW3,600 homes Applied in 2025, still waiting for a decisionWho can move it: Rhondda Cynon Taf Council · planning ref 25/1280/FUL

Plus 1 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Pontypridd 41 MW42 MWnot visible
Vale of Glamorgan 123 MW74 MWnot visible
Cardiff West 0 MW0 MWnot visible
Bridgend 0.8 MW28 MWnot visible
Cardiff North 0.7 MW0 MWnot visible
Caerphilly 20 MW32 MWnot visible

Vale of Glamorgan next door has 123 MW waiting, more than Pontypridd's 41 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.