CONSTITUENCY BRIEFING · ENERGYMAP.APP

Aberafan Maesteg

MP: Stephen Kinnock (Labour) Wales Data to July 2026

Aberafan Maesteg was paid £470k last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 6.4 days. A further 37 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 32,000 homes. A 100 MW battery approved at Rhydypandy Road, Morriston in 2025 would store power that is currently wasted; it has not been built.

Ranks 162 of 650 for clean power approved and not built; 17 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Y Bryn Wind FarmESB / Coriolis Energy Onshore wind 130 MW114,000 homes Refused by the Welsh Government (it decides big energy projects) in 2025Who can move it: the Welsh Government (it decides big energy projects) · planning ref DNS/3264571
Rhydypandy Road, Morriston - Battery Energy Storage SystemStatkraft UK Battery 100 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2025/0855/FUL
Foel TrawsnantPennant Walters Ltd Onshore wind 35 MW31,000 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P2014/0825
Tonmawr - Mynydd Fforch Dwm Wind FarmNaturalis Energy Developments Limited Onshore wind 35 MW31,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DNS/3255801
Chosen Park, Baglan Energy Park - Unit 3 - Battery Storage SystemAldustria Energy Storage Battery 30 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P2025/0064

Plus 2 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Aberafan Maesteg 37 MW313 MW£470k
Neath and Swansea East 27 MW58 MWnot visible
Bridgend 0.8 MW28 MWnot visible
Rhondda and Ogmore 81 MW114 MWnot visible
Merthyr Tydfil and Aberdare 10 MW31 MWnot visible

Rhondda and Ogmore next door has 81 MW waiting, more than Aberafan Maesteg's 37 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call