CONSTITUENCY BRIEFING · ENERGYMAP.APP

Melksham and Devizes

MP: Brian Mathew (Liberal Democrat) England Data to July 2026

Melksham and Devizes has 51 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 18,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 40,462 homes.

Ranks 132 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Norrington Gate Farm, Broughton Gifford - Battery Energy Storage FacilityADV 003 Limited Battery 150 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PL/2022/03914
Studley Farm - Solar Farm & Battery StorageMelksham Calne Green Limited Solar 50 MW18,000 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PL/2021/08690
Potterne Park Farm, Potterne - Solar FarmPotterne Solar Project Limited Solar 50 MW18,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PL/2023/10332
Blounts Court Farm, Potterne - Solar PanelsGreenfield Energy Developments Limited Solar 15 MW5,400 homes Refused by Wiltshire Council in 2025Who can move it: Wiltshire Council · planning ref PL/2024/04926
Byde Mill Solar Farm, Poulshot - Solar FarmAmpyr Solar 14 MW4,900 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PL/2024/11631

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Melksham and Devizes 51 MW133 MWnot visible
South West Wiltshire 74 MW71 MWnot visible
Chippenham 103 MW101 MWnot visible
East Wiltshire 2.3 MW63 MWnot visible
South Cotswolds 194 MW224 MWnot visible
Frome and East Somerset 87 MW34 MWnot visible

South Cotswolds next door has 194 MW waiting, more than Melksham and Devizes's 51 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.